Simulations of field-development planning help improve economics of heavy-oil project

被引:0
|
作者
Teotico D. [1 ]
Schauerte L. [1 ]
Griffith J. [1 ]
Schottle G. [2 ]
Mehl R. [2 ]
机构
[1] Shell, Australia
[2] Halliburton, Australia
来源
SPE Economics and Management | 2010年 / 2卷 / 02期
关键词
Value engineering;
D O I
10.2118/124203-PA
中图分类号
学科分类号
摘要
When Shell began an ultraheavy-oil development in Alberta, Canada, the field plan was based on manual pad positioning without consideration for surface hazards, trajectory constraints, or injector/producer slot requirements arising from the prefabricated-pad configuration. Shell teams were challenged to investigate alternative field-development plans to reduce the initial investment. The volume of wells, surface hazards, trajectory constraints, and pad slot configuration requirements for injector/producer ratios made this a formidable task. Shell leveraged the expertise of third-party consultants and powerful software to generate numerous development scenarios, which enabled the Shell staff to focus on the economics of each plan. An aerial image that delineated surface hazards, an elevation grid, and injector/producer targets were loaded into the 3D subsurfacevisualization environment of the software to generate pad-placement simulations, including trajectory designs. The software followed the Shell planning constraints and avoided all surface hazards. The analyses were conducted for the highest, lowest, and median number of pads. From these three scenarios, a value analysis was plotted. This value analysis enabled the planning team to identify the optimal surface-to-reservoir configuration and to maximize the value of the field by delivering all of the reservoir targets, while minimizing the number of pads needed to drill. The output also yielded field cumulative values, including total and nominal well length, to support future economic analyses. The analysis determined that 87 pads maximized the value of the field when 42-slot configured pads were considered. Additional studies determined that when 50-slot configured pads were considered, more than 99% of the planned reservoir targets could be drilled from 72 major and four or fewer minor pads. In either case, a significant reduction from the original 98 pads was realized. Through the combined efforts of Shell engineers and third-party consultants, as well as the use of state-of-the-art software, this optimization was completed in only 8 worker-weeks. This paper describes the software and processes used to reduce Shell's estimated field-development costs and to minimize the environmental effect of the field by reducing the number of pads required. Copyright © 2010 Society of Petroleum Engineers.
引用
收藏
页码:75 / 79
页数:4
相关论文
共 50 条
  • [31] Heavy-oil Papa-Terra project uses innovative solutions in deep water
    1600, Society of Petroleum Engineers (SPE) (66):
  • [32] Subsurface Sludge Sequestration in Cyclic Steam Stimulated Heavy-Oil Reservoir in Liaohe Oil Field
    Zhong, Liguo
    Liu, Jianbin
    Yuan, Xiaonan
    Wang, Cheng
    Teng, Liyong
    Zhang, Shoujun
    Wu, Fei
    Shen, Wenmin
    Jiang, Cheng
    SPE JOURNAL, 2020, 25 (03): : 1113 - 1127
  • [33] Full-field heavy-oil conversion from cold to hot production
    Jansen, F.E., 1600, Society of Petroleum Engineers (SPE) (64):
  • [34] Reservoir modeling for horizontal-well exploitation of a giant heavy-oil field
    Tankersley, TH
    Waite, MW
    SPE RESERVOIR EVALUATION & ENGINEERING, 2003, 6 (06) : 421 - 425
  • [35] Multi-disciplinary study of the heavy-oil reservoirs in the Armatella Field, Sicily
    Ruvo, L
    Aldegheri, A
    Galimberti, R
    Nembrini, E
    Rossi, L
    Ruspi, R
    PETROLEUM GEOSCIENCE, 2003, 9 (03) : 265 - 276
  • [36] Chemical stimulation at a heavy-oil field: Key considerations, work flow, and results
    Gutierrez, Mauricio
    Bonilla, Fernando
    Gil, Layonel
    Parra, Wilmer
    Campo, Pablo
    Orozco, Alex
    Garcia, Monica
    JPT, Journal of Petroleum Technology, 2018, 70 (03): : 77 - 78
  • [37] Two-wellhead SAGD scheme increases efficiency of heavy-oil development
    Carpenter C.
    JPT, Journal of Petroleum Technology, 2019, 71 (04): : 69 - 70
  • [38] Development and Application of Electrical-Joule-Heating Simulator for Heavy-Oil Reservoirs
    Lashgari, Hamid R.
    Delshad, Mojdeh
    Sepehrnoori, Kamy
    de Rouffignac, Eric
    SPE JOURNAL, 2016, 21 (01): : 87 - 100
  • [40] Heavy-oil solution-gas drive for Hamaca field: Depletion studies and interpretations
    1600, Society of Petroleum Engineers (SPE) (56):