Analytical and numerical load evaluation from excavation shoring on the powerhouse Kirchbichl

被引:0
|
作者
Gloimüller S. [1 ]
Pánová P. [2 ]
Lang G. [1 ]
机构
[1] AFRY Austria GmbH, Strubergasse 30, Salzburg
[2] AFRY Austria GmbH, Kranichberggasse 4, J2, Vienna
来源
Geomechanik und Tunnelbau | 2020年 / 13卷 / 05期
关键词
analytical and numerical load determination; bored pile wall; Cut and cover method; Excavations; Hydro power plants; Powerhouse extension; Soil mechanics; Special type of construction; Structural analysis;
D O I
10.1002/geot.202000031
中图分类号
学科分类号
摘要
Tiroler Wasserkraft AG realized the extension of hydropower plant Kirchbichl located in the Unterinntal built in the 1940s for the first time. The excavation pits were retained by a bored pile wall with jet grouting connections between the piles, supported with up to two bracing horizons. Safety against uplift during construction stage is managed by a deep-set jet grouting plate, which is partially anchored. Due to the dismantling of the bracing during the construction progress a partially load transfer from the bored pile wall on the partly completed concrete construction and the jet grouted plate occurs. This interaction is simulated at the static calculations. The excavation shoring was calculated by using a geotechnical program. The resulting spring supporting forces from geotechnical consideration were used in the finite element model as loads on the new reinforced concrete walls to calculate the necessary reinforcement content during construction sequence. The results from construction sequence were perpetuated at final state of the new powerhouse structure to get the governing reinforcement content. © 2020, Ernst und Sohn. All rights reserved.
引用
收藏
页码:566 / 573
页数:7
相关论文
共 50 条
  • [31] Analytical and Numerical Analyses of Tunnel Excavation Problem Using an Extended Drucker-Prager Model
    Liu, K.
    Chen, S. L.
    Gu, X. Q.
    ROCK MECHANICS AND ROCK ENGINEERING, 2020, 53 (04) : 1777 - 1790
  • [32] Predicting the amount of face seepage during the excavation of the mechanized tunnel, using numerical and analytical methods
    Majid Omidi Arjenaki
    Modeling Earth Systems and Environment, 2022, 8 : 2889 - 2896
  • [33] Numerical Study on Static and Dynamic Load Response of Temporary Support System for Group Tunnels Excavation
    Zeng, Yu
    Huang, Bo
    Zou, Yu
    Bai, Yao
    BUILDINGS, 2022, 12 (10)
  • [35] Analytical prediction and numerical simulation of effect of a deep excavation project of wuhan metro on nearby viaduct
    Hu, Bin
    Wang, Xin-Gang
    Feng, Xiao-La
    Hu, Qi-Chen
    Wang, Wei
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 2014, 36 : 368 - 373
  • [36] Numerical Analyses of the Stress and Limiting Load for Buried Gas Pipelines under Excavation Machine Impact
    Yao, Anlin
    Xu, Taolong
    Zeng, Xiangguo
    Jiang, Hongye
    JOURNAL OF PIPELINE SYSTEMS ENGINEERING AND PRACTICE, 2015, 6 (03)
  • [37] Analytical and numerical computation of the no-load magnetic field in induction motors
    Ionel, DM
    Cistelecan, MV
    COMPEL-THE INTERNATIONAL JOURNAL FOR COMPUTATION AND MATHEMATICS IN ELECTRICAL AND ELECTRONIC ENGINEERING, 1998, 17 (1-3) : 225 - 231
  • [38] Numerical and analytical predictions of the limit load of rectangular two way slabs
    Famiyesin, OOR
    Hossain, KMA
    Chia, YH
    Slade, PA
    COMPUTERS & STRUCTURES, 2001, 79 (01) : 43 - 52
  • [39] Analytical and numerical computation of the no-load magnetic field in induction motors
    Ionel, Dan M.
    Cistelecan, Mihai V.
    COMPEL - The International Journal for Computation and Mathematics in Electrical and Electronic Engineering, 1998, 17 (02): : 225 - 231
  • [40] Numerical Evaluation of Control Measures for Tunnel Deformation Induced by an Oversized Deep Excavation
    Xiao, Xiao
    Li, Ming-Guang
    Wang, Jian-Hua
    Chen, Jin-Jian
    JOURNAL OF AEROSPACE ENGINEERING, 2018, 31 (06)