Study of the monitoring system for double row steel sheet pile cofferdam engineering

被引:1
|
作者
Wang J. [1 ,2 ]
Liu G. [3 ]
机构
[1] Faculty of Engineering, China University of Geosciences, Hubei, Wuhan
[2] CCCC Highway Consultants Co., Ltd., Beijing
[3] CCTEG Xi'an Research Institute, Xi'an
关键词
cofferdam; real-time monitoring; safety;
D O I
10.1504/ijwmc.2022.127589
中图分类号
学科分类号
摘要
The construction monitoring and control standard of the steel sheet pile cofferdam is still the standard of the foundation pit of the civil structure. In this paper, by referring to the literature related to double-wall steel sheet pile cofferdam, the detection content, structure calculation method and error analysis of double-wall steel sheet pile cofferdam project are summarised systematically. To ensure the safety of the cofferdam structure, the automatic monitoring system of steel cofferdam is established to realise the organic combination of real-time monitoring and control of steel cofferdam, so as to take timely measures to ensure the smooth progress of the project and analyse the error which will be used to improve the model and algorithm. Finally, the calculation error between the model and algorithm will shrink and be smaller, making the results more reliable. Copyright © 2022 Inderscience Enterprises Ltd.
引用
收藏
页码:256 / 260
页数:4
相关论文
共 50 条
  • [21] Parameter Study on Double-row Pile in the Combined High Retaining Structure
    Wang, Gang
    Dong, Changrui
    Fang, Zheng
    Chang, Si
    Singh, Jenisha
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2022, 40 (10) : 5233 - 5248
  • [22] Parameter Study on Double-row Pile in the Combined High Retaining Structure
    Gang Wang
    Changrui Dong
    Zheng Fang
    Si Chang
    Jenisha Singh
    Geotechnical and Geological Engineering, 2022, 40 : 5233 - 5248
  • [23] Experimental Study on Stability of Coastal Levee with Double-Row Steel Sheet Piles under Extreme Storm Surge
    Peng, Ming
    Liang, Yaoying
    Zhu, Yan
    Jiang, Qiulu
    Liu, Nianwu
    GEO-EXTREME 2021: CASE HISTORIES AND BEST PRACTICES, 2021, 328 : 425 - 434
  • [24] Development of automatic cooperated welding control system of steel pipe sheet pile
    Nakashima, Jun
    Robot Tokyo, 1996, (110): : 43 - 50
  • [25] State of the art report on steel sheet pile method in geotechnical engineering -development of PFS method
    Otani, J.
    PROCEEDINGS OF THE SECOND INTERNATIONAL CONFERENCE ON PRESS-IN ENGINEERING 2021, 2021, : 15 - 33
  • [26] Numerical Simulation Study on Steel Pipe Row Pile Support of Temporary Road Slope
    Bai, Jian-guang
    Li, Hai-jun
    JORDAN JOURNAL OF MECHANICAL AND INDUSTRIAL ENGINEERING, 2022, 16 (05): : 743 - 752
  • [27] Study on Optimal Pile Length in Load Section of Double-Row Buried Pile under Overtopping Failure Mode
    Li, Xunchang
    Wang, Mingming
    Yang, Wei
    Xu, Rui
    Pang, Xuqing
    APPLIED SCIENCES-BASEL, 2024, 14 (01):
  • [28] Development of a practical design method for double-row anti-sliding pile system
    Xie, Qiang (xieqiang2000@hotmail.com), 1600, E-Journal of Geotechnical Engineering (19):
  • [29] Earth pressure evolution of the double-row long-short stabilizing pile system
    Yongjiang Shen
    Yang Yu
    Fei Ma
    Feilong Mi
    Zhengliang Xiang
    Environmental Earth Sciences, 2017, 76
  • [30] Earth pressure evolution of the double-row long-short stabilizing pile system
    Shen, Yongjiang
    Yu, Yang
    Ma, Fei
    Mi, Feilong
    Xiang, Zhengliang
    ENVIRONMENTAL EARTH SCIENCES, 2017, 76 (16)