Scheduling in a Simple Assembly Robotics Cell to Minimize Earliness and Tardiness

被引:0
|
作者
Munoz-Guevara, John Andres [1 ]
Villegas-Florez, Jairo Alberto [1 ]
Jaramillo-Tabima, Jhannier Jhoan [1 ]
机构
[1] Univ Tecnol Pereira, Fac Ciencias Empresariales, Pereira, Colombia
来源
INGENIERIA | 2024年 / 29卷 / 02期
关键词
robotic assembly cell; tardiness; scheduling; GENETIC ALGORITHM; MACHINE;
D O I
10.14483/23448393.20895
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Background: Robotics Assembly Cells (RAC) have been designed to meet the flexibility requirements demanded by today's globalized market. The objective is to manufacture a vast variety of products at a low cost, which requires equipment with a high level of flexibility, such as robots. The need to schedule a great variety of jobs in an RAC is a very relevant issue, as efficiency and productivity depend on the sequence in which jobs are scheduled. Studies around this matter have developed models with analytical and heuristic approaches, as well as simulation methods and genetic algorithms, seeking to improve performance measures based mainly on time, utilization, and costs. Method: The purpose of this article is to formulate an exact mathematical model using mixed-integer linear programming (MILP) to optimize small scheduling problems. The objective is to minimize the measure of performance related to the tardiness and earliness of jobs. This optimization aims to mitigate the effects of delays in product deliveries, queue times, and work-in-process inventory in subsequent processes. Doing so facilitates adherence to agreed-upon delivery deadlines and prevents bottlenecks in the assembly cell. Results: The proposed mathematical model generates optimal solutions to the job scheduling problem in the assembly cell, which serves as a case study. This addresses the need to minimize tardiness to meet delivery deadlines or minimize earliness while avoiding an increase in work-in-process inventories. The model ensures that optimal scheduling decisions are made to optimize both delivery performance and inventory levels. Conclusions: Due to the NP-hard complexity of the scheduling problem under study, the proposed mathematical model demonstrates computational efficiency in solving scheduling problems with fewer than 20 jobs. The model is designed to handle such smaller-scale problems within a reasonable computational time frame, considering the inherent complexity of the scheduling problem.
引用
收藏
页数:15
相关论文
共 50 条
  • [31] The two stage assembly flowshop scheduling problem to minimize total tardiness
    Ali Allahverdi
    Harun Aydilek
    Journal of Intelligent Manufacturing, 2015, 26 : 225 - 237
  • [32] Scatter Search for Distributed Assembly Flowshop Scheduling to Minimize Total Tardiness
    Yang, Yixin
    Li, Peng
    Wang, Shouyang
    Liu, Bo
    Luo, Yongliang
    2017 IEEE CONGRESS ON EVOLUTIONARY COMPUTATION (CEC), 2017, : 861 - 868
  • [33] Preemption in single machine earliness/tardiness scheduling
    Bulbul, Kerem
    Kaminsky, Philip
    Yano, Candace
    JOURNAL OF SCHEDULING, 2007, 10 (4-5) : 271 - 292
  • [34] Scheduling with earliness–tardiness penalties and parallel machines
    Yasmin A. Rios-Solis
    4OR, 2008, 6 : 191 - 194
  • [35] Minimizing earliness and tardiness costs in stochastic scheduling
    Baker, Kenneth R.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2014, 236 (02) : 445 - 452
  • [36] Simple heuristic to minimize total tardiness in a single machine scheduling problem
    Panneerselvam, R.
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2006, 30 (7-8): : 722 - 726
  • [37] Simple heuristic to minimize total tardiness in a single machine scheduling problem
    R. Panneerselvam
    The International Journal of Advanced Manufacturing Technology, 2006, 30 : 722 - 726
  • [38] Simple heuristic to minimize total tardiness in a single machine scheduling problem
    Panneerselvam, R.
    International Journal of Advanced Manufacturing Technology, 2006, 30 (7-8): : 722 - 726
  • [39] Earliness-tardiness scheduling with setup considerations
    Sourd, F
    COMPUTERS & OPERATIONS RESEARCH, 2005, 32 (07) : 1849 - 1865
  • [40] Parallel machine scheduling with earliness and tardiness penalties
    Sivrikaya-Serifoglu, F
    Ulusoy, G
    COMPUTERS & OPERATIONS RESEARCH, 1999, 26 (08) : 773 - 787