Blasting excavation close to fresh Roller Compacted Concrete, in RCC Dam construction sites

被引:0
|
作者
Ruffato, P. [1 ]
Folchi, R. [2 ]
机构
[1] Webuild, Milan, Italy
[2] Nitrex Srl, Lonato, Brascia, Italy
关键词
D O I
10.1201/9781003440420-23
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
RCC dam construction is a long process which takes years to be completed, and requires precise planning and a tight sequence of activities. Due to planning constraints, RCC placement is to start before the completion of the dam foundation blasting excavation. The purpose of this paper is to demonstrate the possibility to perform blast excavation while in the same foundation area RCC is under placing at a distance in the order of 50m or less to the blasting, and compacted by vibrating rollers. The vibrations generated by rollers at different levels into the RCC were measured and compared with vibrations generated by the nearby excavations executed with explosive. It is assumed that controlled blasting excavation is safe in the vicinity of fresh RCC, if the induced vibrations are in the same order as those generated by rollers during the compaction operations. Laboratory tests on fresh RCC that sensed the reduced vibrations compared to those on RCC that did not, confirm that its material properties are not affected by the controlled blasting. The outcome of this work and added value on an RCC dam construction lies in allowing the excavation of a part of the dam foundations to be completed while RCC concrete placement is already in progress in the other part of the foundation.
引用
收藏
页码:199 / 208
页数:10
相关论文
共 50 条
  • [41] High-speed flow erosion test study on roller compacted concrete dam during construction
    Wang, Xin
    Luo, Shaoze
    Yuan, Qiang
    ANTI-CORROSION METHODS AND MATERIALS, 2012, 59 (04) : 163 - 169
  • [42] CONSTRUCTION TECHNIQUES FOR ROLLER-COMPACTED CONCRETE.
    Stewart, Rita F.
    Schexnayder, Cliff J.
    Transportation Research Record, 1986, : 32 - 37
  • [43] CONSTRUCTION OF ROLLER-COMPACTED CONCRETE PAVEMENTS.
    Pittman, David W.
    Transportation Research Record, 1986, : 13 - 19
  • [44] Coupling Real-time Control of Construction Safety and Progress of Roller Compacted Concrete Dam During the Construction Period
    Chang, Haotian
    Zhong, Denghua
    FRONTIERS OF GREEN BUILDING, MATERIALS AND CIVIL ENGINEERING III, PTS 1-3, 2013, 368-370 : 1454 - 1458
  • [45] A new evaluation of the fatigue design criteria of roller compacted concrete (RCC) pavements
    Sengun, E.
    Alam, B.
    Yaman, I. O.
    Ceylan, H.
    CONSTRUCTION AND BUILDING MATERIALS, 2021, 289
  • [46] Interlayer shear strength of Roller compacted concrete (RCC) with various interlayer treatments
    Liu, Guohua
    Lu, Wenbin
    Lou, Yadong
    Pan, Wenna
    Wang, Zhenyu
    CONSTRUCTION AND BUILDING MATERIALS, 2018, 166 : 647 - 656
  • [47] Appropriate laboratory compaction methods for different types of Roller Compacted Concrete (RCC)
    Schrader, E
    ROLLER COMPACTED CONCRETE DAMS, 2003, : 1037 - 1044
  • [48] The Effect of Mixture Parameters on the Surface Properties of Roller Compacted Concrete (RCC) Pavements
    Shabani, Reza
    Sengun, Emin
    Ozturk, Hande, I
    Yaman, I. Ozgur
    TEKNIK DERGI, 2021, 32 (05): : 11153 - 11174
  • [49] Use of geocomposite drain against rapid-drawdown loading for roller-compacted concrete (RCC) armored earth dam
    Oezer, A. T.
    Bromwell, L. G.
    GEOSYNTHETICS INTERNATIONAL, 2011, 18 (05) : 207 - 220
  • [50] Study on the Properties of Roller Compacted Concrete in the Dam of Jinghong Hydropower Station
    Xie, Jianbin
    He, Tianchun
    Fan, Jing
    Ai, Yongping
    ADVANCES IN CIVIL ENGINEERING, PTS 1-4, 2011, 90-93 : 2541 - +