Development of time–cost trade-off optimization model for construction projects with MOPSO technique

被引:0
|
作者
Agarwal A.K. [1 ]
Chauhan S.S. [1 ]
Sharma K. [1 ]
Sethi K.C. [3 ]
机构
[1] Science, Madhya Pradesh, Gwalior
[2] Civil Engineering Department, Centurion University of Technology and Management, Gajapati
关键词
Construction projects; MOPSO; Multi-mode activities; Pareto-optimal solutions; TCT;
D O I
10.1007/s42107-024-01063-3
中图分类号
学科分类号
摘要
Balancing cost and time present a critical yet conflicting challenge in scheduling of construction projects. In today;s highly competitive construction market, achieving a subtle balance in optimizing objectives (time and cost) is vital for success of projects, requiring project participants to make essential trade-offs. With multi-objective particle swarm optimization (MOPSO), this study presents a time–cost trade-off (TCT) optimization model to overcome the challenges and constraints associated with existing TCT models. The focus is on multi-mode construction project activities, where each mode represents a different option for a construction activity requiring varying amounts of resources, time, and cost. The paper aims to select the best alternatives for project activities. For demonstrating the effectiveness of the developed MOPSO method in generating a set of Pareto-optimal solutions, it is applied to a real case study project. The working of proposed method in simultaneously optimizing two objectives is evaluated against existing trade-off optimization methods. The project team is provided with trade-off plots and an a priori approach to select one of the generated Pareto-optimal solutions. Additionally, this research will benefit the project;s stakeholders by maximizing profits, and the findings of this study can assist organizations and project teams in improving their scheduling choices. © The Author(s), under exclusive licence to Springer Nature Switzerland AG 2024.
引用
收藏
页码:4529 / 4539
页数:10
相关论文
共 50 条
  • [1] Optimization of environmental impacts of construction projects: a time–cost–quality trade-off approach
    S. A. Banihashemi
    Mohammad Khalilzadeh
    A. Shahraki
    M. Rostami Malkhalifeh
    S. S. R. Ahmadizadeh
    [J]. International Journal of Environmental Science and Technology, 2021, 18 : 631 - 646
  • [2] Time-Cost Trade-off Optimization of Construction Projects using Teaching Learning Based Optimization
    Vedat Toğan
    M. Azim Eirgash
    [J]. KSCE Journal of Civil Engineering, 2019, 23 : 10 - 20
  • [3] Time-Cost Trade-off Optimization of Construction Projects using Teaching Learning Based Optimization
    Togan, Vedat
    Eirgash, M. Azim
    [J]. KSCE JOURNAL OF CIVIL ENGINEERING, 2019, 23 (01) : 10 - 20
  • [4] A TRADE-OFF BETWEEN TIME AND COST IN SCHEDULING REPETITIVE CONSTRUCTION PROJECTS
    Zhang, Lihui
    Zou, Xin
    Qi, Jianxun
    [J]. JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2015, 11 (04) : 1423 - 1434
  • [5] Factors affecting time and cost trade-off in multiple construction projects
    Hasan, Musaab Falih
    Mohammed, Sawsan Rasheed
    [J]. ARCHIVES OF CIVIL ENGINEERING, 2022, 68 (02) : 549 - 561
  • [6] Optimization of environmental impacts of construction projects: a time-cost-quality trade-off approach
    Banihashemi, S. A.
    Khalilzadeh, Mohammad
    Shahraki, A.
    Malkhalifeh, M. Rostami
    Ahmadizadeh, S. S. R.
    [J]. INTERNATIONAL JOURNAL OF ENVIRONMENTAL SCIENCE AND TECHNOLOGY, 2021, 18 (03) : 631 - 646
  • [7] Fuzzy Multicriteria Decision-Making Model for Time-Cost-Risk Trade-Off Optimization in Construction Projects
    Alzarrad, M. Ammar
    Moynihan, Gary P.
    Hatamleh, Muhammad T.
    Song, Siyuan
    [J]. ADVANCES IN CIVIL ENGINEERING, 2019, 2019
  • [8] Improvement Optimization Algorithm for Stochastic Discrete Time-cost Trade-off Problems of Construction Projects
    Wang J.
    Tang J.
    Zhou Z.
    Han C.
    [J]. Hunan Daxue Xuebao/Journal of Hunan University Natural Sciences, 2023, 50 (07): : 229 - 238
  • [9] Time-cost-quality trade-off analysis for planning construction projects
    Wang, Tianqi
    Abdallah, Moatassem
    Clevenger, Caroline
    Monghasemi, Shahryar
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (01) : 82 - 100
  • [10] Time-cost trade-off optimization model for retrofitting planning projects using MOGA
    Patil A.S.
    Agarwal A.K.
    Sharma K.
    Trivedi M.K.
    [J]. Asian Journal of Civil Engineering, 2024, 25 (5) : 3823 - 3833