Development of Innovative Integrated Last Planner System (ILPS)

被引:0
|
作者
Mughees Aslam
Zhili Gao
Gary Smith
机构
[1] North Dakota State University,Department of Construction Management and Engineering
[2] National University of Science and Technology,Department of Construction Engineering and Management
[3] North Dakota State University,Department of Construction Management and Engineering
关键词
Integrated last planner system (ILPS); Lean tools and techniques; Shortcomings; Look-ahead planning; Constraint analysis; Visualization;
D O I
暂无
中图分类号
学科分类号
摘要
Last planner system (LPS) has been recognized as one of the most formidable tools for implementing lean construction (LC) and improving construction productivity. The past 25 years have witnessed the sequential development of LPS but still, the construction industry is unable to utilize its full potentials. It was reported that users of LPS were only able to achieve 70% of their weekly assignments with much potential to perform better. Considering it is a complete lean construction tool, LPS is mostly implemented in isolation, thereby exposing many areas that are overlooked and poorly managed. In this study, an effort has been made in developing strategies to overcome LPS implementation challenges by integrating LPS with other available lean tools and techniques. A systematic literature review is carried out, followed by a conceptual development of findings and theories into a robust integrated LPS implementation model. Thirteen (13) major shortcomings in implementing LPS and sixteen (16) lean tools to overcome these shortcomings are identified. Presently, LPS is managed as a single entity. However, due to its vast diversity, all of its stages should be managed independently. In this study, lean tools are integrated within LPS stages to develop the innovative integrated last planner system (ILPS), allowing the management of LPS stages independently. Additionally, a guideline for sequential amalgamation of LPS with the lean tools at different stages is presented to smoothen the ILPS implementation process. The ILPS will facilitate the construction industry in utilizing LPS to its fullest potential. This newly developed ILPS will help the lean practitioners in increasing construction productivity and reducing cost and time.
引用
收藏
页码:701 / 715
页数:14
相关论文
共 50 条
  • [1] Development of Innovative Integrated Last Planner System (ILPS)
    Aslam, Mughees
    Gao, Zhili
    Smith, Gary
    [J]. INTERNATIONAL JOURNAL OF CIVIL ENGINEERING, 2020, 18 (6A) : 701 - 715
  • [2] Last planner and integrated project delivery
    Cho, Seongkyun
    Ballard, Glenn
    [J]. Lean Construction Journal, 2011, 2011 : 67 - 73
  • [3] Last planner system in construction
    Cwik, Katarzyna
    Roslon, Jerzy
    [J]. RSP 2017 - XXVI R-S-P SEMINAR 2017 THEORETICAL FOUNDATION OF CIVIL ENGINEERING, 2017, 117
  • [4] Development of Approach to Support Construction Stakeholders in Implementation of the Last Planner System
    Daniel, Emmanuel Itodo
    Pasquire, Christine
    Dickens, Graham
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2019, 35 (05)
  • [5] Learning from breakdowns in the last planner system®
    Wilkinson, Bruce
    Lowe, Tony
    Pereira, Mauricio
    [J]. Lean Construction Journal, 2020, 2020 : 141 - 153
  • [6] Extending the last planner system® to the entire project
    Ballard, Glenn
    Vaagen, Hajnalka
    Kay, William
    Stevens, Bill
    Pereira, Mauricio
    [J]. Lean Construction Journal, 2020, 2020 : 42 - 77
  • [7] Key requirements of an IT tool based on last planner® system
    Cortes, M. J.
    Herrera, R. F.
    Munoz-La Rivera, F. C.
    Avila-Eca de Matos, B.
    [J]. REVISTA INGENIERIA DE CONSTRUCCION, 2020, 35 (02): : 126 - 134
  • [8] Development of an integrated CAD/CAM system for shoe last
    Chen, Jianliang
    Gong, Youping
    Jin, Tao
    Tong, Shuiguang
    [J]. 2005 IEEE International Conference on Mechatronics and Automations, Vols 1-4, Conference Proceedings, 2005, : 1107 - 1111
  • [9] Lean Construction in the UAE: Implementation of Last Planner System®
    Warid, Osama
    Hamani, Karima
    [J]. Lean Construction Journal, 2023, 2023 : 01 - 20
  • [10] Last planner system results in subcontract construction company
    Andrade, M.
    Arrieta, B.
    [J]. REVISTA DE LA CONSTRUCCION, 2011, 10 (01): : 36 - 52