An 8.2m diameter, 40m deep shaft for Crossrail is being constructed below the 10m deep basement of the Moorhouse development near Moorgate in the City of London. The depth of the shaft is such that it will penetrate through stiff London Clay and will be founded at the bottom of the Lambeth Group. The shaft is being constructed after the Moorhouse structure has been completed and the design of the Moorhouse foundations places tight constraints on acceptable ground movements due to construction of the shaft. Furthermore, the shaft needs to be designed to accommodate future ground movements associated with construction of Crossrail. The paper describes the complex relationship between the foundations of Moorhouse, the draught relief shaft and the future Crossrail assets. The optimised design includes extensive slip coating and base grouting of the Moorhouse piles, a complex temporary works dewatering system around the shaft and the option to carry out additional dewatering from within the shaft during construction. Control of ground movements through the Lambeth Group was perceived to be a particular problem in relationship to destressing the ground around the Moorhouse piles. To prevent long-term settlement of these piles, provision was made for radial grouting to "restress" the ground should the need arise.
引用
收藏
页码:173 / 182
页数:10
相关论文
共 50 条
  • [1] Construction of a deep shaft for Crossrail
    McNamara, Andrew
    Roberts, Toby
    Morrison, Paul
    Holmes, Gary
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-GEOTECHNICAL ENGINEERING, 2008, 161 (06) : 299 - 309
  • [2] Crossrail project: infrastructure design and construction (Volume 3)
    Oloke, David
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-CIVIL ENGINEERING, 2017, 170 (02) : 58 - 58
  • [3] Groundwater monitoring of the deep aquifer for the construction phase of the Crossrail project
    Lawrence, U.
    Menkiti, C. O.
    Black, M.
    QUARTERLY JOURNAL OF ENGINEERING GEOLOGY AND HYDROGEOLOGY, 2018, 51 (01) : 38 - 48
  • [4] Ultra-deep shaft construction
    Kirkbride, Mark
    Stringer, Nigel
    Tunnels and Tunnelling International, 2002, 34 (06): : 38 - 40
  • [5] Delivering the Moorgate shaft base slab on Crossrail, UK
    Douglas, Adrian
    Smith, Marcus
    Hunter, Jonathan
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-CIVIL ENGINEERING, 2015, 168 (04) : 159 - 169
  • [6] Design and construction of tunnel and shaft plugs
    Marold, James W.
    Kolenda, Peter
    NORTH AMERICAN TUNNELING 2008, PROCEEDINGS, 2008, : 334 - 344
  • [7] Research progress of deep shaft construction mechanics
    He M.
    Meitan Xuebao/Journal of the China Coal Society, 2021, 46 (03): : 726 - 746
  • [8] Canary Wharf Crossrail station cofferdam, London, UK: design, construction and performance
    Travers, Ronan
    Yeow, Hoe-Chian
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-GEOTECHNICAL ENGINEERING, 2014, 167 (02) : 169 - 181
  • [9] The design of the Crossrail tunnels in UK
    Thomas, Alun
    Geomechanik und Tunnelbau, 2021, 14 (04): : 340 - 346
  • [10] A Primary Support Design for Deep Shaft Construction Based on the Mechanism of Advanced Sequential Geopressure Release
    Zhao, Xingdong
    Deng, Lei
    Zhou, Xin
    Zhao, Yifan
    Guo, Zhenpeng
    PROCESSES, 2022, 10 (07)