Machine Learning-Based Prediction of Missing Components for Assembly - a Case Study at an Engineer-to-Order Manufacturer

被引:5
|
作者
Burggraef, Peter [1 ]
Wagner, Johannes [1 ]
Heinbach, Benjamin [1 ]
Steinberg, Fabian [1 ]
机构
[1] Univ Siegen, Dept Mech Engn, Chair Int Prod Engn & Management IPEM, D-57076 Siegen, Germany
关键词
Predictive models; Data models; Production; Manufacturing; Companies; Analytical models; Schedules; Production control; assembly; prediction methods; lead time reduction; machine learning; supervised learning; classification algorithms; regression analysis; data analysis; LEAD TIME PREDICTION; PERFORMANCE; ENVIRONMENT; REGRESSION; VOLUME;
D O I
10.1109/ACCESS.2021.3075620
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
For manufacturing companies, especially for machine and plant manufacturers, the assembly of products in time has an essential impact on meeting delivery dates. Often missing individual components lead to a delayed assembly start, hereinafter referred to as assembly start delayers. Identifying the assembly start delayers early in the production process can help to set countermeasures to meet the required delivery dates. In order to achieve this, we set up 24 prediction models on four different levels of detail utilizing different machine learning-algorithms - six prediction models on every level of detail - and applying a case-based research approach in order to identify the model with the highest model quality. The modeling approach on the four levels of detail is different. The models on the coarsest level of detail predict assembly start delayers utilizing a classification approach. The models on the three finer levels of detail predict assembly start delayers via a regression of different lead times and subsequent postprocessing operations to identify the assembly start delayers. After training of the 24 prediction models based on a real data set of a machine and plant manufacturer and evaluating their model quality, the classification model utilizing a Gradient Boosting classifier showed best results. Thus, performing a binary classification to identify assembly start delayers was the best modelling approach. With the achieved results, our study is a first approach to predict assembly start delayers and gives insights in the performance of different modeling approaches in the area of a production planning and control.
引用
收藏
页码:105926 / 105938
页数:13
相关论文
共 50 条
  • [1] Multi-Project Scheduling Cost Optimization in a Machine Manufacturer Engineer-to-Order
    Farizal
    Rachman, Amar
    Tandean, Tifani
    Sudarto, Sumarsono
    Takahashi, Katsuhiko
    MAKARA JOURNAL OF TECHNOLOGY, 2016, 20 (01): : 13 - 18
  • [2] Implications of automation in engineer-to-order production: a case study
    Sjobakk, Borge
    Thomassen, Maria
    Alfnes, Erlend
    ADVANCES IN MANUFACTURING, 2014, 2 (02) : 141 - 149
  • [3] Implementing Lean in Engineer-to-Order Industry: A Case Study
    Kjersem, Kristina
    Halse, Lise Lillebrygfjeld
    Kiekebos, Peter
    Emblemsvag, Jan
    ADVANCES IN PRODUCTION MANAGEMENT SYSTEMS: INNOVATIVE PRODUCTION MANAGEMENT TOWARDS SUSTAINABLE GROWTH (AMPS 2015), PT II, 2015, 460 : 248 - 255
  • [4] Implications of automation in engineer-to-order production:a case study
    Borge Sjobakk
    Maria Kollberg Thomassen
    Erlend Alfnes
    AdvancesinManufacturing, 2014, 2 (02) : 141 - 149
  • [5] Implications of automation in engineer-to-order production: a case study
    Børge Sjøbakk
    Maria Kollberg Thomassen
    Erlend Alfnes
    Advances in Manufacturing, 2014, 2 : 141 - 149
  • [6] Designing an Engineer-To-Order Performance Measurement System: A Case Study
    Sjobakk, Borge
    Bakas, Ottar
    ADVANCES IN PRODUCTION MANAGEMENT SYSTEMS: INNOVATIVE AND KNOWLEDGE-BASED PRODUCTION MANAGEMENT IN A GLOBAL-LOCAL WORLD, APMS 2014, PT III, 2014, 440 : 473 - 480
  • [7] Impact of material data in assembly delay prediction—a machine learning-based case study in machinery industry
    Fabian Steinberg
    Peter Burggaef
    Johannes Wagner
    Benjamin Heinbach
    The International Journal of Advanced Manufacturing Technology, 2022, 120 : 1333 - 1346
  • [8] Performance measurement in design engineering: A case study in an engineer-to-order company
    Sousa, GWL
    Venuto, JJ
    Coelho, RA
    Van Aken, EM
    ENGINEERING MANAGEMENT: IT'S ABOUT PEOPLE, PROCEEDINGS, 2001, : 364 - 373
  • [9] Impact of material data in assembly delay prediction-a machine learning-based case study in machinery industry
    Steinberg, Fabian
    Burggaef, Peter
    Wagner, Johannes
    Heinbach, Benjamin
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2022, 120 (1-2): : 1333 - 1346
  • [10] Procurement organisation in project-based setting: a multiple case study of engineer-to-order companies
    Moretto, Antonella
    Patrucco, Andrea Stefano
    Walker, Helen
    Ronchi, Stefano
    PRODUCTION PLANNING & CONTROL, 2022, 33 (9-10) : 847 - 862