Construction of a Jet-Grouted Backup Seepage Cut-Off Wall in the John Hart North Earthfill Dam

被引:0
|
作者
Gazzarrini, Paolo [1 ]
Siu, David [2 ]
Jungaro, Stephen [3 ]
机构
[1] Sea Sky Geotech Inc, 11-2246 Folkestone Way, W Vancouver, BC V7S 2X7, Canada
[2] BC Hydro & Power Author, 6911 Southpoint Dr, Burnaby, BC V3N 4X8, Canada
[3] Matcon Excavat & Shoring Ltd, 2208 Hartley Ave, Coquitlam, BC V3K 6X3, Canada
关键词
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
To provide additional protection to a 70 year-old dam in case of a seismic event, the local utility company, BC Hydro, required the construction of a backup seepage cut-off wall in the right abutment of the John Hart North Earthfill Dam, using jet-grouting, a well-known technique that uses a high-velocity jet of grout mix at high pressure (300 to 500 bars) to erode and simultaneously mix cementitious grout with the soil in situ. The main challenge was the use of these high pressures during construction of the seepage cut-off wall in the dam fills and foundation soil while avoiding reservoir drawdown, to minimize the risk of hydro-fracturing or hydro-jacking in the embankment. The contractor carried out a field trial in a safe area with similar soil conditions and, with the utility, developed a jet-grouting procedure that minimized the risks. The paper describes the jet-grouting procedures, grout mix used, results of the field trial, and safety and environmental precautions implemented on site to reach successful completion.
引用
收藏
页码:92 / 101
页数:10
相关论文
共 14 条
  • [1] Probabilistic investigation on defective jet-grouted cut-off wall with random geometric imperfections
    Pan, Y.
    Liu, Y.
    Chen, E. J.
    GEOTECHNIQUE, 2019, 69 (05): : 420 - 433
  • [2] A theoretical model for estimating the water-tightness of jet-grouted cut-off walls with geometric imperfections
    Wang, Kai
    Li, Zhaoping
    Zheng, Hao
    Xu, Xuezhao
    He, Huafei
    COMPUTERS AND GEOTECHNICS, 2021, 138
  • [3] Construction experience of concrete cut-off wall in Xiaolangdi dam project
    Li, Ligang
    Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering, 1999, 21 (05): : 625 - 627
  • [4] Seepage Through a Homogeneous Earth-Fill Dam with a Cut-Off Wall on a Permeable Foundation
    Bestuzheva A.S.
    Anakhaev K.K.
    Power Technology and Engineering, 2020, 54 (02): : 147 - 153
  • [5] Cut-off wall, diaphragm wall, piling and grouting works for the construction oftheJannah Dam in Lebanon
    Adnan, Mazin
    Baltruschat, Michael
    Abdo, Georges
    WASSERWIRTSCHAFT, 2023, 113 (06) : 48 - 51
  • [6] Construction and performance of the Karkheh dam complementary cut-off wall: an innovative engineering solution
    Heidarzadeh, Mohammad
    Mirghasemi, Ali A.
    Niroomand, Habib
    Eslamin, Faramarz
    INTERNATIONAL JOURNAL OF CIVIL ENGINEERING, 2019, 17 (6B) : 859 - 869
  • [7] Construction and performance of the Karkheh dam complementary cut-off wall: an innovative engineering solution
    Mohammad Heidarzadeh
    Ali A. Mirghasemi
    Habib Niroomand
    Faramarz Eslamin
    International Journal of Civil Engineering, 2019, 17 : 859 - 869
  • [8] Study on Anti-seepage Effect of Xiongjiagang Earth-Rock Dam Based on Cut-off Wall Schemes
    Han Yong
    Ke Chuanfang
    2010 INTERNATIONAL SYMPOSIUM ON MULTI-FIELD COUPLING THEORY OF ROCK AND SOIL MEDIA AND ITS APPLICATIONS, 2010, : 548 - 552
  • [9] Analysis on seepage effects of plastic concrete cut-off wall in construction and operation period of hydropower station tail channel
    Yan Guoxin
    Wu Wei
    ADVANCES IN CIVIL AND INDUSTRIAL ENGINEERING IV, 2014, 580-583 : 1816 - +
  • [10] Construction of deep plastic concrete cut-off wall in upstream coffer dam of Punatsangchhu-I Hydropower Project, Bhutan
    Gajbhiye, P. K.
    PROCEEDINGS OF THE CONFERENCE ON RECENT ADVANCES IN ROCK ENGINEERING (RARE 2016), 2016, 91 : 353 - 360