Completion delay risk management: A dynamic risk insurance approach

被引:7
|
作者
Kokkaew, Nakhon [1 ]
Wipulanusat, Warit [1 ]
机构
[1] Walailak Univ, Dept Civil Engn, Nakhon Si Thammarat 80160, Thailand
关键词
uncertainty; completion risk insurance; envelope method; monte carlo simulation; CONSTRUCTION; GUARANTEES; PROJECTS;
D O I
10.1007/s12205-014-1128-4
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In the construction of an infrastructure project, completion delay is one of the major risks to the financial outlook of an infrastructure project under construction. During the construction phase, if the project is delayed, project managers can take specific actions to shorten the duration of certain activities on the critical path in order to restore the project to its original schedule. However, not all management actions to shorten the duration of activities are cost-effective: the cost of reducing some activities' duration may exceed the savings. Risk that project managers cannot economically reduce through management feedback reactions should instead be transferred to third parties such as insurance companies that have risk pooling capacity. In this paper, we present a novel way of managing completion delay risk through "dynamic risk insurance" by combining a technique known as the envelope method with a stochastic-based Monte Carlo method. Two important features of this implementation of dynamic completion risk insurance are (1) a stochastic risk premium between the contractor and the surety over the course of construction and (2) evolution of the risk premium as a function of management feedback reaction. Finally, two illustrative examples, a BOT road and a commercial building, demonstrate how the proposed model may be applied in practice. The new model of dynamic risk insurance presented in this paper may improve risk management practice in large-scale construction projects that are loaded with uncertainty.
引用
收藏
页码:1599 / 1608
页数:10
相关论文
共 50 条
  • [1] Completion delay risk management: A dynamic risk insurance approach
    Nakhon Kokkaew
    Warit Wipulanusat
    [J]. KSCE Journal of Civil Engineering, 2014, 18 : 1599 - 1608
  • [2] Dynamic Completion Risk Insurance for Mitigating Construction Delay in Infrastructure Project Finance
    Nakhon, Kokkaew
    Feng, Dong
    Warit, Wipulanusat
    [J]. PROCEEDINGS OF 2012 INTERNATIONAL CONFERENCE ON CONSTRUCTION & REAL ESTATE MANAGEMENT, VOLS 1 AND 2, 2012, : 485 - 491
  • [3] THE MANAGEMENT OF CATASTROPHE INSURANCE RISK IN A STOCHASTIC APPROACH
    Szkutnik, Wlodzimierz
    [J]. ANALYSIS OF INTERNATIONAL RELATIONS 2018: METHODS AND MODELS OF REGIONAL DEVELOPMENT, 2018, : 95 - 103
  • [4] Lapse tables for lapse risk management in insurance: a competing risk approach
    Milhaud, Xavier
    Dutang, Christophe
    [J]. EUROPEAN ACTUARIAL JOURNAL, 2018, 8 (01) : 97 - 126
  • [5] Refining the Approach to Compensation - An Insurance Based Risk Management Approach
    Burden, Robert
    [J]. EUROCHOICES, 2012, 11 (02) : 32 - 38
  • [6] Explicit solutions to correlation matrix completion problems, with an application to risk management and insurance
    Georgescu, Dan I.
    Higham, Nicholas J.
    Peters, Gareth W.
    [J]. ROYAL SOCIETY OPEN SCIENCE, 2018, 5 (03):
  • [7] Risk Management and Insurance
    Mark Butterworth
    [J]. Risk Management, 2003, 5 (4) : 75 - 76
  • [8] Cash Flow Risk Management in the Property/Liability Insurance Industry: A Dynamic Factor Modeling Approach
    Wen, Min-Ming
    Lin, H. J. Abraham
    Born, Patricia H.
    Yang, Charles
    Wang, Chun
    [J]. NORTH AMERICAN ACTUARIAL JOURNAL, 2018, 22 (02) : 309 - 322
  • [9] Risk management of time varying floors for dynamic portfolio insurance
    Ben Ameur, H.
    Prigent, J-L
    [J]. EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2018, 269 (01) : 363 - 381
  • [10] Development of Dynamic Intelligent Risk Management Approach
    Sarkheyli, Azadeh
    Song, William Wei
    Sarkheyli-Hagele, Arezoo
    [J]. 2018 3RD INTERNATIONAL CONFERENCE ON COMPUTATIONAL INTELLIGENCE AND APPLICATIONS (ICCIA), 2018, : 128 - 132