An evolutionary stochastic discrete time-cost trade-off method

被引:4
|
作者
Hussein, Bahaa [1 ]
Moselhi, Osama [1 ]
机构
[1] Concordia Univ, Dept Bldg Civil & Environm Engn, Sir George Williams Campus, Montreal, PQ H3G 1M8, Canada
关键词
evolutionary optimization methods; discrete time-cost trade-off; uncertainty analysis; joint confidence level; CONSTRUCTION TIME; OPTIMIZATION; ALGORITHM;
D O I
10.1139/cjce-2018-0352
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This study introduces a newly developed method for optimized time-cost trade-off under uncertainty. It identifies the optimal execution mode for each project activity that results in minimizing the overall project cost and (or) duration while satisfying a specified joint confidence level of both time and cost. The method uses an evolutionary-based algorithm along with a design generator of experiments and blocking techniques. The developed method accounts for managerial flexibility towards the selection of execution modes. This accommodates experience-based judgement of project managers in this process. Hence, the second fold of the developed method is a completely randomized experiment module that depicts the main effect of changing an activity mode on the project total cost and overall duration. The method provides the decision-maker a guideline for making well-informed implementation strategies. The results obtained demonstrate benefits and accuracy of the developed method and its applicability for large-scale projects.
引用
收藏
页码:581 / 600
页数:20
相关论文
共 50 条
  • [1] Stochastic construction time-cost trade-off analysis
    Feng, CW
    Liu, L
    Burns, SA
    [J]. JOURNAL OF COMPUTING IN CIVIL ENGINEERING, 2000, 14 (02) : 117 - 126
  • [2] TIME-COST TRADE-OFF FOR AIRLINERS
    HARTLEY, K
    CORCORAN, W
    [J]. JOURNAL OF INDUSTRIAL ECONOMICS, 1978, 26 (03): : 209 - 222
  • [3] Improvement Optimization Algorithm for Stochastic Discrete Time-cost Trade-off Problems of Construction Projects
    Wang, Jia
    Tang, Jingqi
    Zhou, Zhongbao
    Han, Congji
    [J]. Hunan Daxue Xuebao/Journal of Hunan University Natural Sciences, 2023, 50 (07): : 229 - 238
  • [4] A hybrid genetic algorithm for the discrete time-cost trade-off problem
    Sonmez, Rifat
    Bettemir, Onder Halis
    [J]. EXPERT SYSTEMS WITH APPLICATIONS, 2012, 39 (13) : 11428 - 11434
  • [5] Research on the Hierarchical Discrete Time-Cost Trade-Off Problem for Program
    Chen, Liangwei
    Zhang, Jingwen
    Peng, Wuliang
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2022, 148 (07)
  • [6] Network analysis algorithm for the solution of discrete time-cost trade-off problem
    Önder Halis Bettemir
    M. Talat Birgönül
    [J]. KSCE Journal of Civil Engineering, 2017, 21 : 1047 - 1058
  • [7] Discrete particle swarm optimization method for the large-scale discrete time-cost trade-off problem
    Aminbakhsh, Saman
    Sonmez, Rifat
    [J]. EXPERT SYSTEMS WITH APPLICATIONS, 2016, 51 : 177 - 185
  • [8] A discrete-time approximation technique for the time-cost trade-off in pert networks
    Azaron, Amir
    Sakawa, Masatoshi
    Tavakkoli-Moghaddam, Reza
    Safaei, Nima
    [J]. RAIRO-OPERATIONS RESEARCH, 2007, 41 (01) : 61 - 81
  • [9] MINLP optimization model for the nonlinear discrete time-cost trade-off problem
    Klansek, Uros
    Psunder, Mirko
    [J]. ADVANCES IN ENGINEERING SOFTWARE, 2012, 48 : 6 - 16
  • [10] Network Analysis Algorithm for the Solution of Discrete Time-Cost Trade-off Problem
    Bettemir, Onder Halis
    Birgonul, M. Talat
    [J]. KSCE JOURNAL OF CIVIL ENGINEERING, 2017, 21 (04) : 1047 - 1058