Research of Scheduling Management in Warship Scheduled Repair Project

被引:0
|
作者
Zhou, Shilei [1 ]
Zheng, Yingfeng [1 ]
Jiang, Zhang [2 ]
Duan, Mengqiang [3 ]
机构
[1] Naval Univ Engn, Power Engn Coll, Wuhan 430033, Peoples R China
[2] Naval Equipment Div Representat Off Jiangam, Shanghai 201913, Peoples R China
[3] Naval Equipment Div Representat, Huludao 125005, Peoples R China
来源
SUSTAINABLE DEVELOPMENT AND ENVIRONMENT II, PTS 1 AND 2 | 2013年 / 409-410卷
关键词
scheduled repair; practical progress vanguard line; buffer management; schedule control;
D O I
10.4028/www.scientific.net/AMM.409-410.1564
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The buffer setting and management mechanism in Critical chain method was combined with practical progress vanguard line in this paper. Then the information statistical and analysis methods of project schedule was given, and the methods are applied in project scheduling management of warship scheduled repair. With the application analysis in maintenance project shows that this methods can identify the activity chain which really lead to the lag of project scheduling. This shows that the method was given in this paper presents an applicable value for actual warship scheduled repair project scheduling management.