Multi-project scheduling with two-stage decomposition

被引:38
|
作者
Can, Anil [1 ]
Ulusoy, Gunduz [1 ]
机构
[1] Sabanci Univ, TR-34956 Istanbul, Turkey
关键词
Multiple projects; Multiple modes; Scheduling; Decomposition; Genetic algorithm; GENETIC ALGORITHM; RULES; HEURISTICS; MODELS; DATE;
D O I
10.1007/s10479-014-1555-0
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
We consider a non-preemptive, zero time lag multi-project scheduling problem with multiple modes and limited renewable and nonrenewable resources. A two-stage decomposition approach is adopted to formulate the problem as a hierarchy of 0-1 mathematical programming models. In stage one; each project is reduced to a macroactivity with macro-modes. The macro-activities are combined into a single macro-activity network over which the macro-activity scheduling problem (MP) is defined, where the objective is the maximization of the net present value with positive cash flows and the renewable resource requirements are time-dependent. An exact solution procedure and a genetic algorithm (GA) approach are proposed for solving the MP. A GA is also employed to generate an initial solution for the exact solution procedure. The first stage terminates with a post-processing procedure to distribute the remaining resource capacities. Using the start times and the resource profiles obtained in stage one, each project is scheduled in stage two for minimum makespan. Three new test problem sets are generated with 81, 84 and 27 problems each, and three different configurations of solution procedures are tested.
引用
收藏
页码:95 / 116
页数:22
相关论文
共 50 条
  • [1] Multi-project scheduling with two-stage decomposition
    Anıl Can
    Gündüz Ulusoy
    Annals of Operations Research, 2014, 217 : 95 - 116
  • [2] A multi-agent system for distributed multi-project scheduling with two-stage decomposition
    Li, Feifei
    Xu, Zhe
    PLOS ONE, 2018, 13 (10):
  • [3] Two-stage algorithm for resource-constrained multi-project scheduling problem
    Chen J.-J.
    Tong S.-R.
    Ye Z.-G.
    Zhang J.-W.
    Wang Y.
    Nie Y.-F.
    Zhang Y.-Q.
    Chen, Jun-Jie (junjiechen75@nwpu.edu.cn), 2013, Northeast University (35): : 2013 - 2020
  • [4] A DECOMPOSITION APPROACH TO MULTI-PROJECT SCHEDULING
    DECKRO, RF
    WINKOFSKY, EP
    HEBERT, JE
    GAGNON, R
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1991, 51 (01) : 110 - 118
  • [5] A two-stage genetic programming framework for Stochastic Resource Constrained Multi-Project Scheduling Problem under New Project Insertions
    Chen, HaoJie
    Zhang, Jian
    Li, Rong
    Ding, Guofu
    Qin, Shengfeng
    APPLIED SOFT COMPUTING, 2022, 124
  • [6] A three-stage decomposition algorithm for decentralized multi-project scheduling under uncertainty
    Liu, Dongning
    Xu, Zhe
    Li, Feifei
    COMPUTERS & INDUSTRIAL ENGINEERING, 2021, 160
  • [7] Multi-project scheduling
    Ohmae, Yoshitsugu
    Hasegawa, Susumu
    Okuda, Minoru
    Journal of information processing, 1992, 15 (02) : 267 - 279
  • [8] MULTI-PROJECT SCHEDULING - ANALYSIS OF PROJECT PERFORMANCE
    KURTULUS, IS
    NARULA, SC
    IIE TRANSACTIONS, 1985, 17 (01) : 58 - 66
  • [9] MULTI-PROJECT SCHEDULING WITH RESOURCE CONSTRAINS
    HIRAOKA, T
    BULLETIN OF THE JSME-JAPAN SOCIETY OF MECHANICAL ENGINEERS, 1980, 23 (185): : 1929 - 1936
  • [10] A Two-Stage Algorithm Based on 12 Priority Rules for the Stochastic Distributed Resource-Constrained Multi-Project Scheduling Problem With Multi-Skilled Staff
    Yu, Yining
    Xu, Zhe
    Zhao, Song
    IEEE ACCESS, 2023, 11 : 29554 - 29565