Construction of the Inter-Island Tunnel - Boston Harbor Project

被引:0
|
作者
Ferguson, DW
Shufflebotham, RL
Page, TL
Stewart, AJ
机构
关键词
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Inter-island Tunnel is a 7.7 kilometer (25,160 foot) long by 3.5 meter (11.5 feet) diameter concrete lined tunnel through the Cambridge formation below Boston Harbor. Constructed as part of the Boston Harbor Project, this tunnel will bring untreated waste water from the MWRA's South System headworks facility at Nut island in Quincy, MA to the new Deer Island treatment plant. A myriad of problems delayed the construction of the tunnel. These problems included salt water inflows of over 22,000 liters (5,812 gallons) per minute, a major fire in the access shaft, weak rock and soil collapsing on the tunnel boring machine, and hand mining operations.