Quantification of Productivity Changes Due to Work Schedule Changes in Construction Projects. A Case Study

被引:3
|
作者
Arriagada, Ricardo E. [1 ]
Alarcon C, Luis F. [1 ]
机构
[1] Pontificia Univ Catolica Chile, Fac Engn, Santiago, Chile
来源
REVISTA DE LA CONSTRUCCION | 2014年 / 13卷 / 01期
关键词
Probabilistic model; working day extended; productivity loss; mining project; case study;
D O I
10.4067/S0718-915X2014000100001
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In a copper-molybdenum open pit mine in Chile, a collective labor dispute in April 2012 halted work on the site; the main problem was the negotiation of unified work schedules for contractors, subcontractors and their own staff. To avoid conflicts that could delay this project, the parties agreed to submit to arbitration by an external agency, to determine and quantify the existence of lost productivity caused by the change of work schedules. The external agency considered three basic elements: a) the temporal dimension to allow the comparison of two work schedules, b) the acceptable range of productivity losses associated with these schedules; and c) an unbiased mechanism to allocate a productivity loss within the range associated with each schedule. This paper presents the analysis of productivity loss when work schedules are extended, the method utilized, and the results obtained. This probabilistic model randomly assigns discrete values of productivity loss for each day of the work schedules, and uses inefficiency ranges from industry research; this allows a non-biased, easy to implement, comparison of work schedules.
引用
收藏
页码:9 / 14
页数:6
相关论文
共 50 条
  • [1] Quantifying costs of the productivity loss due to schedule changes in construction projects
    Lee, Jae-Seob
    [J]. ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2023, 30 (01) : 56 - 73
  • [2] PROPOSAL TO IMPROVE PRODUCTIVITY IN THE CONSTRUCTION PROJECTS. STUDY CASE MAXPLOT S.A. COMPANY
    Sellan, Neyva Astudillo
    Quezada-Torres, Walter David
    [J]. REVISTA UNIVERSIDAD Y SOCIEDAD, 2024, 16 (02): : 491 - 497
  • [3] Promoting the inclusion of families through the development of Work Projects. A case study
    Ruiz Torres, Maria del Carmen
    Merida Serrano, Rosario
    [J]. REVISTA COMPLUTENSE DE EDUCACION, 2016, 27 (03): : 943 - 961
  • [4] Student group projects. A case study
    Saadat, S.
    Rickman, R.
    Lawrence, J.
    [J]. International Journal of Environmental Studies A & B, 1995, 47 (01):
  • [5] USE OF BIM WITH PHOTOGRAMMETRY SUPPORT IN SMALL CONSTRUCTION PROJECTS. CASE STUDY FOR COMMERCIAL FRANCHISES
    Loredo Conde, Antonio J.
    Garcia-Sanz-Calcedo, Justo
    Reyes Rodriguez, Antonio M.
    [J]. JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2020, 26 (06) : 513 - 523
  • [6] Industrial digital design changes' impact on courses, labs and projects.
    Coowar, R
    [J]. COMPUTERS AND THEIR APPLICATIONS: PROCEEDINGS OF THE ISCA 12TH INTERNATIONAL CONFERENCE, 1997, : 6 - 9
  • [7] Shoreline Changes Due to the Construction of Ports: Case Study-Calabria (Italy)
    Foti, Giandomenico
    Barbaro, Giuseppe
    Barilla, Giuseppina Chiara
    Mancuso, Pierluigi
    [J]. JOURNAL OF MARINE SCIENCE AND ENGINEERING, 2023, 11 (12)
  • [8] Exploring Project Complexity Relations to Scope Changes in Construction Projects: A Case Study of NEC Projects in South Africa
    Lukhele, Themba
    Botha, Brink
    Mbanga, Sijekula
    [J]. CONSTRUCTION ECONOMICS AND BUILDING, 2021, 21 (02): : 18 - 33
  • [9] Documentation and constitution of claims in construction projects caused by delays and changes to the schedule by means of software solutions
    Dokumentation und nachweisführung bei störungen und verzögerungen im bauablauf mit hilfe von softwarelösungen
    [J]. Ripberger, A., 2005, VDI Verlag GMBH
  • [10] Productivity Metrics and Its Implementations in Construction Projects: A Case Study of Singapore
    Shan, Ming
    Li, Yu-Shan
    Hwang, Bon-Gang
    Chua, Jia-En
    [J]. SUSTAINABILITY, 2021, 13 (21)