Numerical Simulation Study on Ventilation Optimization Design of Extra-Long Double-Line Mountain Tunnels with Parallel Heading: A Case Study

被引:1
|
作者
Guo, Weidong [1 ]
Chen, Lei [2 ]
Liu, Guoqiang [3 ]
Wang, Juntao [3 ]
Shi, Shaoshuai [1 ]
Bu, Lin [1 ]
机构
[1] Shandong Univ, Sch Qilu Transportat, Jinan 250061, Peoples R China
[2] Shandong Univ, Sch Civil Enginerring, Jinan 250061, Peoples R China
[3] China Railway 19th Bur Grp Sixth Engn Co, Wuxi 214028, Peoples R China
来源
APPLIED SCIENCES-BASEL | 2022年 / 12卷 / 23期
基金
中国博士后科学基金;
关键词
extra-long mountain tunnel; parallel heading; ventilation optimization design; CFD; CARBON-MONOXIDE; AIR-FLOW; PERFORMANCE;
D O I
10.3390/app122312416
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
There are many issues affecting multi-hole parallel tunneling and long tunnel ventilation, such as insufficient fresh air supplied at the tunnel face, pollution by contaminated winds, and uncoordinated work among multiple fans. In view of these issues, this paper uses the numerical simulation software Fluent combined with the orthogonal analysis test method, and, based on the actual working conditions of Yuelongmen Tunnel on the Chenglan Line, simulates the parameters of the duct, the installation position of the jet fan at the cross channel, and the combined operation status of multiple fans. The main conclusions are as follows: (1) the primary factor affecting the CO discharge from the tunnel face is the distance between the exit of the duct and the tunnel face, and the secondary factor is the diameter of the duct, while the position of the duct is the least influential factor; (2) the jet fan at the intersection of the cross channel should be set close to the pollution source in such a way as to prevent the jet from hitting the windward side of the cross channel and thereby avoid causing the contaminated wind to contaminate the adjacent tunnel; (3) in tunnels in which blasting operations do not occur, the simultaneous use of high-power air supplies and jet fans will reduce the air pressure in the tunnel, generate an air pressure difference with the adjacent tunnel, trap polluted air, and reduce the ventilation effect.
引用
收藏
页数:17
相关论文
共 16 条
  • [1] Simulation Study on Combined Clapboard and Air Channel Ventilation for Extra-long Tunnels in Arctic-Alpine Regions
    Lyu, Xiaoyun
    Liang, Qingguo
    Zhou, Ren
    Liu, Quyao
    Cao, Shenghui
    Wu, Xiaohui
    [J]. Tiedao Xuebao/Journal of the China Railway Society, 2024, 46 (06): : 181 - 188
  • [2] Study on the utilization of non-mechanical ventilation power in extra-long highway tunnels with shafts
    Wang, Yongdong
    Zheng, Rongjun
    Bai, Wenjun
    Qin, Zhenjie
    Chai, Lunlei
    Wan, Shantong
    Yan, Shuai
    [J]. JOURNAL OF WIND ENGINEERING AND INDUSTRIAL AERODYNAMICS, 2022, 221
  • [3] Experimental study on the performance of synergistic ventilation system combining shaft with mechanical ventilation in extra-long road tunnels
    Zhu, Bin
    Cong, Haiyong
    Yu, Binshan
    Shao, Zhuyu
    Ye, Lili
    Bi, Yubo
    Zeng, Yiping
    [J]. TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2024, 147
  • [4] Random Forests-Based Operational Status Perception Model in Extra-Long Highway Tunnels with Longitudinal Ventilation: A Case Study in China
    [J]. Chen, Jianxun (chenjx1969@chd.edu.cn), 1600, Hindawi Limited, 410 Park Avenue, 15th Floor, 287 pmb, New York, NY 10022, United States (2018):
  • [5] Random Forests-Based Operational Status Perception Model in Extra-Long Highway Tunnels with Longitudinal Ventilation: A Case Study in China
    Qian, Chao
    Chen, Jianxun
    Luo, Yanbin
    Li, Shuguang
    [J]. JOURNAL OF ADVANCED TRANSPORTATION, 2018,
  • [6] Field Monitoring and Numerical Simulation Study on Mechanical Characteristics of Extra-long Highway Tunnel
    Li, Xun
    He, Chuan
    Xu, Guowen
    [J]. PROGRESS IN CIVIL ENGINEERING, PTS 1-4, 2012, 170-173 : 1450 - 1454
  • [7] Optimization of ventilation and dust removal parameters in plateau extra-long tunnel inclined shaft based on orthogonal numerical simulation test method
    Yang, Xiangdong
    Jiang, Zhongan
    Chen, Jihe
    Chen, Ya
    Yang, Bin
    [J]. Construction and Building Materials, 2024, 455
  • [8] Research on Calculating Traffic Capacity in Extra-Long Subsea Tunnels-A Case Study of the Qingdao Jiaozhou Bay Subsea Tunnel
    Xing, Ruru
    Li, Zimu
    Cai, Xiaoyu
    Rong, Xiaonan
    Yang, Tao
    Peng, Bo
    [J]. SUSTAINABILITY, 2023, 15 (09)
  • [9] A new ventilation system for extra-long railway tunnel construction by using the air cabin relay: A case study on optimization of air cabin parameters length
    Tao, Yuchun
    Hu, Hui
    Zhang, Heng
    Zhang, Gang
    Hao, Zihan
    Wang, Lu
    [J]. JOURNAL OF BUILDING ENGINEERING, 2022, 45
  • [10] Field Monitoring and Numerical Simulation Study for Mechanical Characteristics of Extra-long Highway Tunnel under Complex Geological Condition
    Li, Xun
    He, Chuan
    Wang, Shi-min
    [J]. 2011 AASRI CONFERENCE ON ARTIFICIAL INTELLIGENCE AND INDUSTRY APPLICATION (AASRI-AIIA 2011), VOL 3, 2011, : 457 - 460