Induction causing Smart Grid Communication Failure, a Case Study from Hydro-Quebec

被引:0
|
作者
Lacroix, M. [1 ]
Foy, D. Chan [2 ]
机构
[1] Vizimax Inc, Longueuil, PQ, Canada
[2] Hydro Quebec, Montreal, PQ, Canada
关键词
Analog modem; Electromagnetic induction; Power system transients; Smart Grid; Surge protection;
D O I
暂无
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
Hydro-Quebec has started a Smart Grid project in 2003. Among the different telecommunication technologies, Hydro-Quebec has chosen the Public Telephone Infrastructure for financial reasons. However, telecommunication metallic lines are potentially exposed to voltage induction caused by current circulating on nearby electric lines. Voltage-limiting devices are used to protect communications equipment against voltage surges that can reach a very high level during a power fault. This paper presents a case where classical protection schemes of wire-line communication, combined with a high level of equipment electrical robustness requirement have not been sufficient to prevent in-service equipment failures. The problem investigation results are presented, along with solutions to prevent it.
引用
收藏
页数:5
相关论文
共 50 条
  • [1] HYDRO-QUEBEC FIBER STUDY
    BOULET, L
    [J]. LASER FOCUS WITH FIBEROPTIC TECHNOLOGY, 1980, 16 (03): : 8 - 8
  • [2] CASE-STUDY ON THE INTEGRATION OF A NONUTILITY INDUCTION GENERATOR TO THE HYDRO-QUEBEC DISTRIBUTION NETWORK
    BELHOMME, R
    PLAMONDON, M
    NAKRA, H
    DESROSIERS, D
    GAGNON, C
    [J]. IEEE TRANSACTIONS ON POWER DELIVERY, 1995, 10 (03) : 1677 - 1684
  • [3] Hydro-Quebec grid code for wind farm interconnection
    Bernard, S
    Beaulieu, D
    Trudel, G
    [J]. 2005 IEEE POWER ENGINEERING SOCIETY GENERAL MEETING, VOLS, 1-3, 2005, : 1248 - 1252
  • [4] Assessment of ENERCON WEC Grid Performance based on Hydro-Quebec System Requirements: a cooperation between ENERCON and Hydro-Quebec
    Fecteau, Martin
    Langlois, Charles-Eric
    Marques, Jeferson
    Jaskulski, Igor
    Mendonca, Angelo
    [J]. 9TH INTERNATIONAL WORKSHOP ON LARGE-SCALE INTEGRATION OF WIND POWER INTO POWER SYSTEMS AS WELL AS ON TRANSMISSION NETWORKS FOR OFFSHORE WIND POWER PLANTS, 2010, : 510 - 518
  • [5] Case Study of the Impact of a Magnetic Storm on a Hydro-Quebec Distribution Feeder
    Tessier, J-L.
    Simard, G.
    [J]. 2008 IEEE POWER & ENERGY SOCIETY GENERAL MEETING, VOLS 1-11, 2008, : 3081 - +
  • [6] Uncertainty and investment in electricity generation with an application to the case of Hydro-Quebec
    Chaton, C
    Doucet, JA
    [J]. ANNALS OF OPERATIONS RESEARCH, 2003, 120 (1-4) : 59 - 80
  • [7] THE FISCAL AND FINANCIAL POLITICS OF ELECTRIC UTILITIES - THE CASE OF HYDRO-QUEBEC
    BERNARD, JT
    GREEN, ST
    [J]. CANADIAN PUBLIC POLICY-ANALYSE DE POLITIQUES, 1988, 14 (03): : 239 - 244
  • [8] Hydro-Quebec's smart station system keeps 16 substations in sync
    Mereb, J.
    Baracos, P.
    [J]. Electrical World, 1993, 207 (12): : 90 - 92
  • [9] Analysis of the Grid Code on Synthetic Inertia of Wind Turbine Generators in Hydro-Quebec TransEnergie
    Kang, Yong Cheol
    Cho, Dongho
    Kim, Kyu-Ho
    [J]. Transactions of the Korean Institute of Electrical Engineers, 2023, 72 (12): : 1593 - 1604
  • [10] HYDRO-QUEBEC MULTIPLE SVC APPLICATION CONTROL STABILITY STUDY
    GERINLAJOIE, L
    SCOTT, G
    BREAULT, S
    LARSEN, EV
    BAKER, DH
    IMECE, AF
    [J]. IEEE TRANSACTIONS ON POWER DELIVERY, 1990, 5 (03) : 1543 - 1551