Stability and resource allocation in project planning

被引:95
|
作者
Leus, R [1 ]
Herroelen, W [1 ]
机构
[1] Katholieke Univ Leuven, Operat Management Grp, Dept Appl Econ, B-3000 Louvain, Belgium
关键词
D O I
10.1080/07408170490447348
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The majority of resource-constrained project scheduling efforts assume perfect information about the scheduling problem to be solved and a static deterministic environment within which the precomputed baseline schedule is executed. In reality, project activities are subject to considerable uncertainty, which generally leads to numerous schedule disruptions. In this paper, we present a resource allocation model that protects a given baseline schedule against activity duration variability. A branch-and-bound algorithm is developed that solves the proposed resource allocation problem. We report on computational results obtained on a set of benchmark problems.