Bridge across the River Vah's Reservoir Hricov and over the road I/18, Motorway D3 in km 7.500

被引:0
|
作者
Dubsik, Vladimir [1 ]
Tanevski, Zoran [2 ]
Salek, Martin [1 ]
机构
[1] Eurovia CS As, Div Bridges & Struct, K Hajum 946, Prague 15500 5, Czech Republic
[2] Ceska Doka Bednici Tech Spol Sro, Avii 868, Prague 19600 9, Czech Republic
关键词
road; bridge;
D O I
10.1016/j.proeng.2016.08.272
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This bridge structure is designed as twin bridge of total length 1.40 km, the structure has only two expansion joints in its length. Each bridge structure is designed as precast concrete girder with 29 and 30 spans. Three methods of casting were designed for this project, symmetrical cantilevers (part 3); stationary (part 1) and movable scaffolding system (part 2 and 4). The cross section of part 1,2 and 4 is double "T" beam, part 3 is box girder. Because of shortage of time all parts of structure had to be built together. Construction of the bridge has started in December 2014, the main prestressed concrete superstructure should be finished until December 2016 and all remaining works should be finalized in 2017. (C) 2016 The Authors. Published by Elsevier Ltd.
引用
收藏
页码:91 / 96
页数:6
相关论文
共 2 条
  • [1] D3 flyover over route I-18, railway and Hricov reservoir
    Sliwka, Pavel
    Svoboda, Pavel
    Barton, Jaroslav
    [J]. BRIDGES IN DANUBE BASIN 2016 - NEW TRENDS IN BRIDGE ENGINEERING AND EFFICIENT SOLUTION FOR LARGE AND MEDIUM SPAN BRIDGES, 2016, 156 : 451 - 457
  • [2] Arch bridge across the D3 motorway at 93,156 km for a local road
    Cap, David
    Svoboda, Milan
    Svoboda, Ondrej
    [J]. 19TH CZECH CONCRETE DAY 2012 / 19 BETONARSKE DNY 2012, 2012, : 62 - 66