A decision making method for congested transmission lines of KEPCO system

被引:0
|
作者
Cha, JM [1 ]
Oh, KH [1 ]
Lee, B [1 ]
Song, KY [1 ]
机构
[1] Daejin Univ, Dept EE, Pocheon 487711, Kyeonggi Do, South Korea
关键词
decision making; Sugeno's fuzzy integral; transmission line reinforcement planning;
D O I
暂无
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
In this paper, fuzzy theory is used to quantify some subjective criteria to consider uncertain factors for transmission line reinforcement planning. As it can be easily applied to multi attribute decision making problems such as power system planning, Sugeno's fuzzy integral is also used in the proposed method. To verify the proposed algorithm, some bottle-neck lines me searched for the case that the amount of Maximal Load Supplying Capability(MLSC) is small using the results of contingency analysis for Korea Electric Power Corporation(KEPCO)'s 345 kV transmission line in 1998. And several feasible alternatives are composed for line reinforcement which can solve the bottle-neck problem in KEPCO system.
引用
收藏
页码:1425 / 1429
页数:5
相关论文
共 50 条
  • [1] Transmission system reliability evaluation of KEPCO system in face of deregulation
    Moon, SP
    Choo, JB
    Jeon, DH
    Kim, HS
    Choi, JS
    Billinton, R
    [J]. 2002 IEEE POWER ENGINEERING SOCIETY SUMMER MEETING, VOLS 1-3, CONFERENCE PROCEEDINGS, 2002, : 713 - 718
  • [2] Optimal decision-making method of transmission lines' maintenance sequence under extreme ice disasters
    Wang, Haitao
    Yang, Zedong
    Wang, Ning
    Jiang, Haiyang
    Cui, Yu
    Han, Jinchi
    Li, Shuguang
    Wang, Changjiang
    [J]. Energy Conversion and Economics, 2023, 4 (03): : 171 - 178
  • [3] A decision tree based method for fault classification in transmission lines
    Shahrtash, S. M.
    Jamehbozorg, A.
    [J]. 2008 IEEE/PES TRANSMISSION & DISTRIBUTION CONFERENCE & EXPOSITION, VOLS 1-3, 2008, : 1039 - 1043
  • [4] Transmission System Upgrading - Analyzing the Alternatives for Final Decision Making
    Chinnasamy, Palanichamy
    Nadarajan, Sundar Babu
    [J]. INTERNATIONAL JOURNAL OF EMERGING ELECTRIC POWER SYSTEMS, 2006, 6 (02): : 1 - 16
  • [5] Transmission system expansion planning of KEPCO System(Youngnam area) using fuzzy set theory
    Kim, H
    Moon, S
    Choi, J
    Lee, C
    Wang, JY
    Billinton, R
    [J]. 2002 IEEE POWER ENGINEERING SOCIETY SUMMER MEETING, VOLS 1-3, CONFERENCE PROCEEDINGS, 2002, : 535 - 540
  • [6] Probabilistic reliability evaluation for 765KV transmission lines in KEPCO grid expansion planning
    Tran, Trungtinh
    Kwon, Jungji
    Choi, Jaeseok
    Jeon, Donghun
    Han, Gyoungnam
    [J]. 2006 INTERNATIONAL CONFERENCE ON PROBABILISTIC METHODS APPLIED TO POWER SYSTEMS, VOLS 1 AND 2, 2006, : 389 - 392
  • [7] Identification method of key transmission lines in power system
    Kang, Zhongjian
    Li, Changchao
    Yu, Hongguo
    Zheng, Shichao
    Ri, Kihong
    [J]. Dianli Zidonghua Shebei/Electric Power Automation Equipment, 2020, 40 (04): : 63 - 70
  • [8] Study of decision making method diagnostic expert system
    Qi, Yi
    Shen, Shi-Tuan
    Li, Yi-Hua
    Bai, Liang
    [J]. Hangkong Xuebao/Acta Aeronautica et Astronautica Sinica, 2003, 24 (02): : 147 - 151
  • [9] Identification of Simultaneously Congested Transmission Lines in Power Systems Operation and Market Analysis
    Javadi, Milad
    Hong, Mingguo
    Angarita, Ruth N.
    Hosseini, Seyed Hossein
    Jiang, John Ning
    [J]. IEEE TRANSACTIONS ON POWER SYSTEMS, 2017, 32 (03) : 1772 - 1781
  • [10] A Criticality Assessment Method for Power Transmission Lines in Power System
    Liu, Wenying
    Liang, Cai
    [J]. ADVANCED RESEARCH IN MATERIAL SCIENCE AND MECHANICAL ENGINEERING, PTS 1 AND 2, 2014, 446-447 : 817 - +