摘要
Shaft 26B of New York City's Third Water Tunnel was constructed by Frontier-Kemper Constructors, Inc. of Evansville, Indiana. The 176.8 m (580 ft) deep shaft will serve as the construction shaft for the Manhattan spur of Water Tunnel No. 3. Twelve m (40 ft) of overburden was supported by a rectangular cofferdam. This shaft was excavated in 13 months, through 164.6 m (540 ft) of rock, using 24,040 kg (26.5 tons) of explosives. Concrete lining cycles included the installation of stainless steel pipes embedded in the lining as the shaft advanced. A total of 635 m (2,084 linear feet) of stainless steel pipe was installed.