Groundwater-mud control and safety thickness of curtain grouting for the Junchang Tunnel: A case study

被引:36
|
作者
Liu, Jin-Quan [1 ,2 ,3 ]
Chen, Wei-Zhong [4 ]
Yuen, Ka-Veng [1 ,2 ]
Zhou, Xiao-Sheng [5 ]
机构
[1] Univ Macau, State Key Lab Internet Things Smart City, Macau, Peoples R China
[2] Univ Macau, Dept Civil & Environm Engn, Macau, Peoples R China
[3] Chinese Acad Sci, Quanzhou Inst Equipment Mfg, Haixi Inst, Quanzhou 362000, Fujian, Peoples R China
[4] Chinese Acad Sci, State Key Lab Geomech & Geotech Engn, Inst Rock & Soil Mech, Wuhan 430071, Hubei, Peoples R China
[5] Guangxi Xinda Highway Co Ltd, Nanning 530021, Guangxi, Peoples R China
关键词
Groundwater control; Weathered granite; Ground condition; Safety thickness; Field investigation; WATER INRUSH; ROCK MASS; WEATHERING CLASSIFICATION; KARST TUNNEL; ANTAMINA DAM; GROUTABILITY; SYSTEM; MODEL; PERU;
D O I
10.1016/j.tust.2020.103429
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Junchang tunnel is a part of a major project in the Censhui highway in Guangxi province, China. The weathered granite part of the tunnel is approximately 180 m long with two lines and four lanes. Numerous water and mud inrush disasters frequently occurred in the weathered granite area, leading to serious economic loss and challenge to the constructors. Therefore, continuous grouting was carried out for the entire weathered part of the tunnel. This paper describes its curtain grouting for disasters prevention. Detailed discussion is presented on the safety thickness after grouting and the challenges encountered under different hydraulic-geological conditions. Specifically, a water and mud inrush model for the nonlinear flow and mass transfer behavior of weathered granite was used to evaluate the safety thickness in this project. Then, field studies with twenty-five grouting cycles and excavations were conducted to investigate the effective safety thickness. Negative correlation was observed between the safety thickness and the rock classification index [BQ]. Numerical simulation and field tests demonstrated that the thickness l should be larger than 3 m, and, in most cases, 5 m was sufficient when [BQ] < 72.5. When [BQ] >= 72.5, l should be between 1.5 m and 3 m. Based on the field data, an empirical formula was developed to determine the thickness under different values of [BQ]. The research findings serve as an important reference for future projects in similar stratum.
引用
收藏
页数:16
相关论文
共 50 条
  • [1] Groundwater control and curtain grouting for tunnel construction in completely weathered granite
    Liu, Jinquan
    Chen, Weizhong
    Yuan, Jingqiang
    Li, Changjun
    Zhang, Qingyan
    Li, Xiaofei
    BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT, 2018, 77 (02) : 515 - 531
  • [2] Groundwater control and curtain grouting for tunnel construction in completely weathered granite
    Jinquan Liu
    Weizhong Chen
    Jingqiang Yuan
    Changjun Li
    Qingyan Zhang
    Xiaofei Li
    Bulletin of Engineering Geology and the Environment, 2018, 77 : 515 - 531
  • [3] Groundwater Inrush Control and Parameters Optimization of Curtain Grouting Reinforcement for the Jingzhai Tunnel
    Li, Gan
    Ma, Weibin
    Tian, Siming
    Hongbo, Zhou
    Huabin, Fan
    Zou, Wenhao
    GEOFLUIDS, 2021, 2021
  • [4] Grouting for water and mud inrush control in weathered granite tunnel: A case study
    Liu, Jin-Quan
    Yuen, Ka-Veng
    Chen, Wei-Zhong
    Zhou, Xiao-Sheng
    Wei-Wang
    ENGINEERING GEOLOGY, 2020, 279
  • [5] Grouting Treatment of Water and Mud Inrush in Fully Weathered Granite Tunnel: A Case Study
    Niu, Jiandong
    Sun, Yong
    Wang, Bin
    Zhang, Keneng
    Huang, Youhan
    Huang, Shiwu
    Yu, Jiaqin
    Qiu, Liangliang
    GEOFLUIDS, 2020, 2020
  • [6] Groundwater control in open-pit mine with grout curtain using modified lake mud: a case study in East China
    Yuan S.
    Han G.
    Liang Y.
    Arabian Journal of Geosciences, 2021, 14 (12)
  • [7] Study on whole section curtain grouting technique and parameters optimization in subsea NATM tunnel
    Zhang Z.-Q.
    Li H.-Y.
    He C.
    Tiedao Xuebao/Journal of the China Railway Society, 2011, 33 (02): : 86 - 90
  • [8] Grouting for Tunnel Stability Control and Inadequate Grouting Section Recognition: A Case Study of Countermeasure of Giant Karst Cave
    Peng, Peng
    Peng, Feng
    Sun, Zhenyu
    Zhang, Dingli
    APPLIED SCIENCES-BASEL, 2022, 12 (23):
  • [9] Grouting to minimize settlements prior to tunnel excavation - A case study
    Heenan, DM
    Xu, M
    GROUTING AND GROUND TREATMENT, VOL 2, PROCEEDINGS, 2003, (120): : 1546 - 1556
  • [10] Optimizing the Grouting Design for Groundwater Inrush Control in Completely Weathered Granite Tunnel: An Experimental and Field Investigation
    Zheng, Weihua
    Wang, Dengwu
    Li, Guijin
    Qin, Lin
    Luo, Kai
    Liu, Jinquan
    SUSTAINABILITY, 2019, 11 (13):