Monitoring of Time and Cost Variances of Schedule Using Simple Earned Value Method Indicators

被引:14
|
作者
Przywara, Daniel [1 ]
Rak, Adam [1 ]
机构
[1] Opole Univ Technol, Dept Civil Engn & Construct Proc, Fac Civil Engn & Architecture, PL-45063 Opole, Poland
来源
APPLIED SCIENCES-BASEL | 2021年 / 11卷 / 04期
关键词
earned value method— EVM; time variances; cost variances; schedule; MANAGEMENT; DURATION;
D O I
10.3390/app11041357
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
The Planning and implementation of construction projects are difficult processes and are burdened with many risk elements. The budget spread over time, which is developed on the basis of the schedule, presents the expected distribution of costs throughout the duration of the works, which during the implementation of the project is subject to constant changes resulting from time, cost, and organizational factors. Managing construction contracts requires managers to be able to analyze on an ongoing basis the variances of production costs-from the values calculated in the offer cost estimate and assumed in the Budgeted Cost of Work Scheduled. The article attempts to analyze the emerging time and cost deviations using proprietary time variances from the schedule (T/S) and variances from planned costs (T/C) monitoring, based on simple indicators of the earned value method (EVM). An example of construction of a multi-family housing development was used to study the variances of planned and incurred costs.
引用
收藏
页码:1 / 13
页数:12
相关论文
共 50 条
  • [1] APPLICATION OF EARNED VALUE METHOD IN COST/SCHEDULE MANAGEMENT OF AN INTERNATIONAL CONFERENCE
    Ren, Hui
    ICIM 2010: PROCEEDINGS OF THE TENTH INTERNATIONAL CONFERENCE ON INDUSTRIAL MANAGEMENT, 2010, : 284 - 288
  • [2] Cost/Schedule Monitoring and Forecasting for Project Based on Earned Value Management (EVM)
    Huang, Jianwen
    Pan, Huimin
    Li, Yan
    Zhu, Yiting
    Liao, Zaiyi
    ADVANCED CONSTRUCTION TECHNOLOGIES, 2014, 919-921 : 1437 - +
  • [3] COST, SCHEDULE, AND TIME VARIANCES AND INTEGRATION
    CARR, RI
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1993, 119 (02): : 245 - 265
  • [4] Beyond Earned Value Management: A Graphical Framework for Integrated Cost, Schedule and Risk Monitoring
    Acebes, Fernando
    Pajares, Javier
    Manuel Galan, Jose
    Lopez-Paredes, Adolfo
    SELECTED PAPERS FROM THE 26TH IPMA (INTERNATIONAL PROJECT MANAGEMENT ASSOCIATION), WORLD CONGRESS, 2013, 74 : 181 - 189
  • [5] Understanding Schedule Progress Using Earned Value and Earned Schedule Techniques at Path-Level
    Capone, Christian
    Narbaev, Timur
    ADVANCES IN PRODUCTION MANAGEMENT SYSTEMS: ARTIFICIAL INTELLIGENCE FOR SUSTAINABLE AND RESILIENT PRODUCTION SYSTEMS, PT V, 2021, 634 : 244 - 251
  • [6] Analysis of the Earned Value Management and Earned Schedule Techniques in Complex Hydroelectric Power Production Projects: Cost and Time Forecast
    Urgiles, P.
    Claver, J.
    Sebastian, M. A.
    COMPLEXITY, 2019, 2019
  • [7] Performance measurement of schedule and cost analysis by using earned value management for a residential building
    Sruthi, Mullapudi Durga
    Aravindan, Achuthan
    MATERIALS TODAY-PROCEEDINGS, 2020, 33 : 524 - 532
  • [8] Using Enhancement Method to Improve Earned Value Index to Achieve an Accurate Project Time and Cost Estimation
    Attarzadeh, Iman
    Hock, Ow Siew
    INTERNATIONAL CONFERENCE ON FUTURE COMPUTER AND COMMUNICATIONS, PROCEEDINGS, 2009, : 421 - 425
  • [9] Project success indicators focusing on residential projects: Are schedule performance index and cost performance index accurate measures in earned value?
    Kim, Sang-chul
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2009, 36 (11) : 1700 - 1710
  • [10] Schedule-cost Joint Management of Thermal Power Construction Project Based on Improved Earned Value Method
    Wu, Meiqiong
    Wang, Meng
    Niu, Dongxiao
    PROCEEDINGS OF THE 2017 3RD INTERNATIONAL CONFERENCE ON HUMANITIES AND SOCIAL SCIENCE RESEARCH (ICHSSR 2017), 2017, 121 : 35 - 39