It's very important for power generation companies to improve the level of management, enterprise quota maybe a good to achieve this. Based on Three Gorges Power Station, we attempted to investigate the quota complitation of overhaul operations. In this paper, the expenses of quota complitation constitutes with five parts: (1) depreciation charges (2) equipment repairs, installation and removal fees (3) labor costs (4) fuel and power costs (5) other expenses.