Study of probabilistic safety assessment for a reprocessing plant

被引:0
|
作者
Wang, Renze [1 ]
Zhang, Jiangang [1 ]
Li, Guoqiang [1 ]
Zhuang, Dajie [1 ]
Yang, Yapeng [1 ]
Feng, Zongyang [1 ]
Jia, Linsheng [1 ]
Wang, Ning [1 ]
Liang, Boning [1 ]
机构
[1] China Inst Radiat Protect, Taiyuan 030006, Peoples R China
关键词
SYSTEM;
D O I
10.1088/1755-1315/467/1/012078
中图分类号
TE [石油、天然气工业]; TK [能源与动力工程];
学科分类号
0807 ; 0820 ;
摘要
According to China's nuclear power development plan, the demand for construction of more large-scale spent fuel reprocessing plant (RP) is increased. Nuclear safety is very important in the whole process of nuclear fuel cycle, and the safety supervision of RPs mainly draws lessons from the safety supervision of nuclear power plants (NPPs). The industry had come to realize that it could not eliminate all risks through its defense-in-depth principle and design basis accident methodologies. All nuclear power countries with advanced reprocessing industry such as the United Kingdom, France and Japan have carried out probabilistic safety assessment (PSA) research for RPs. This paper takes Chinese pilot RP as the research object. First, failure mode and effect analysis (FMEA) and master logic diagram (MLD) methodologies were adopted to identify initiating events (IEs), and then IEs were grouped. After that, fault tree (FT) analysis was performed to various accidents - red oil explosion, fire and criticality. Reliabilities of public systems - power and water and compressed air supply systems were modelled and analysed with GO methodology. And then, consequences of typical accidents were assessed. Finally, application of risk-informed technology in the reprocessing facility was investigated. In brief, PSA for a pilot RP was explored in this paper, and the results could be used as reference for Chinese commercial RP.
引用
收藏
页数:8
相关论文
共 50 条
  • [1] SAFETY DESIGN AND SAFETY ASSESSMENT OF ROKKASHO REPROCESSING PLANT
    MATSUOKA, S
    [J]. JOURNAL OF THE ATOMIC ENERGY SOCIETY OF JAPAN, 1993, 35 (10): : 864 - 873
  • [2] Application of probabilistic safety assessment to Rokkasho reprocessing plant (III) in-cell solvent fire
    Tamauchi, Yoshikazu
    Segawa, Satoshi
    Hayashi, Yoshiaki
    Matsuoka, Shingo
    Kurosu, Katsuya
    [J]. Transactions of the Atomic Energy Society of Japan, 2011, 10 (03) : 170 - 184
  • [3] Assessment of safety culture at a nuclear reprocessing plant
    Lee, T
    [J]. WORK AND STRESS, 1998, 12 (03): : 217 - 237
  • [4] NEW RISK ASSESSMENT METHOD FOR A REPROCESSING PLANT: QUANTITATIVE SAFETY ASSESSMENT
    Tamauchi, Yoshikazu
    Miyata, Takashi
    Takebe, Kazumi
    Hayashi, Yoshiaki
    Matsuoka, Shingo
    Hayashi, Kazuya
    Kurosu, Katsuya
    [J]. NUCLEAR TECHNOLOGY, 2013, 181 (02) : 303 - 316
  • [5] ASSESSMENT OF THE ENGINEERED SAFETY ASPECTS OF THE PLANNED GERMAN REPROCESSING PLANT
    STURMER, W
    [J]. ATOMWIRTSCHAFT-ATOMTECHNIK, 1985, 30 (04): : 206 - 208
  • [6] Study of a plant walkdown procedure utilizing a plant-specific probabilistic safety assessment
    Onoue, A
    Kojima, S
    Bley, DC
    Wreathall, J
    [J]. PROBABILISTIC SAFETY ASSESSMENT AND MANAGEMENT (PSAM 4), VOLS 1-4, 1998, : 2749 - 2753
  • [7] Probabilistic Safety Assessment of a Typical Chemical Process Plant
    Ghuge, N. S.
    Shukla, Pragati
    Manivannan, S.
    Mandal, D.
    [J]. RELIABILITY, SAFETY AND HAZARD ASSESSMENT FOR RISK-BASED TECHNOLOGIES, 2020, : 37 - 50
  • [9] Fuzzy probability on reliability study of nuclear power plant probabilistic safety assessment: A review
    Purba, Julwan Hendry
    [J]. PROGRESS IN NUCLEAR ENERGY, 2014, 76 : 73 - 80
  • [10] EXPERIENCE BOUNDS ON NUCLEAR-PLANT PROBABILISTIC SAFETY ASSESSMENT
    FRAGOLA, JR
    SHOOMAN, ML
    [J]. PROCEEDINGS ANNUAL RELIABILITY AND MAINTAINABILITY SYMPOSIUM, 1992, (SYM): : 157 - 165