Effects of the application of activity calendars on the distribution of project duration in PERT networks

被引:31
|
作者
Hajdu, Miklos [1 ]
机构
[1] Szent Istvan Univ, Dept Construct Management, Ybl Miklos Fac Architecture & Civil Engn, Budapest, Hungary
关键词
PERT; Distribution of project duration; Activity calendars; Monte Carlo simulation; RANDOM-VARIABLES; COMPLETION-TIME; APPROXIMATION; MODEL;
D O I
10.1016/j.autcon.2013.05.025
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The Program Evaluation and Review Technique (PERT) has been criticized for the proposed (beta) distribution of the activities, the three-point estimation method, the assumption of task independence and the assumed distribution of the project duration since its birth. Developments and generalizations of the succeeding years and decades were mostly aimed at resolving these issues. However, there are still pending questions that have not been examined in detail, if at all. One of these issues is the effect of activity calendars on the distribution of the project duration. Using a simple artificially created project we prove that the application of activity calendars has a greater influence on the distribution of the project duration than any of the above-mentioned criticisms. In the absence of analytic solutions, a robust tool performing Monte Carlo simulations has been used for calculations. (C) 2013 The Author. Published by Elsevier B.V. All rights reserved.
引用
收藏
页码:397 / 404
页数:8
相关论文
共 50 条