Tropical optimization technique in bi-objective project scheduling under temporal constraints

被引:3
|
作者
Krivulin, Nikolai [1 ]
机构
[1] St Petersburg State Univ, Univ Skaya Nab 7-9, St Petersburg 199034, Russia
基金
俄罗斯基础研究基金会;
关键词
Decision analysis; Multiple criteria evaluation; Max-plus algebra; Tropical optimization; Time-constrained project scheduling;
D O I
10.1007/s10287-020-00374-5
中图分类号
O1 [数学]; C [社会科学总论];
学科分类号
03 ; 0303 ; 0701 ; 070101 ;
摘要
We consider a project that consists of a set of activities performed in parallel under constraints on their start and finish times, including start-finish precedence relationships, release start times, release end times, and deadlines. The problems of interest are to decide on the optimal schedule of the activities to minimize both the maximum flow-time over all activities, and the project makespan. We formulate these problems as bi-objective optimization problems in the framework of tropical mathematics which investigates the theory and applications of algebraic systems with idempotent operations and has various applications in management science and operations research. Then, the use of methods and techniques of tropical optimization allows to derive complete Pareto-optimal solutions of the problems in a direct explicit form ready for further analysis and straightforward computation. We discuss the computational complexity of the solution and give illustrative examples.
引用
收藏
页码:437 / 464
页数:28
相关论文
共 50 条
  • [1] Tropical optimization technique in bi-objective project scheduling under temporal constraints
    Nikolai Krivulin
    Computational Management Science, 2020, 17 : 437 - 464
  • [2] A stochastic bi-objective project scheduling model under failure of activities
    Rezaei, Fatemeh
    Najafi, Amir Abbas
    Demeulemeester, Erik
    Ramezanian, Reza
    ANNALS OF OPERATIONS RESEARCH, 2024, 338 (01) : 453 - 476
  • [3] Bi-objective Optimization for Resource-constrained Robust Construction Project Scheduling
    Wanlin Liu
    Li Ge
    Chunli Qu
    Shun Yang
    KSCE Journal of Civil Engineering, 2024, 28 : 15 - 28
  • [4] Bi-objective Optimization for Resource-constrained Robust Construction Project Scheduling
    Liu, Wanlin
    Ge, Li
    Qu, Chunli
    Yang, Shun
    KSCE JOURNAL OF CIVIL ENGINEERING, 2024, 28 (01) : 15 - 28
  • [5] Bi-objective robust project scheduling with resource constraints and flexible activity execution lists
    Liu, Huiran
    Qu, Shaojian
    Li, Renjie
    Razaa, Hassan
    COMPUTERS & INDUSTRIAL ENGINEERING, 2021, 156 (156)
  • [6] Bi-Objective Multi-Mode Project Scheduling Under Risk Aversion
    Gutjahr, Walter J.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2015, 246 (02) : 421 - 434
  • [7] Bi-objective optimization of maintenance scheduling for power systems
    Hadjaissa, B.
    Ameur, K.
    Cheikh, S. M. Ait
    Essounbouli, N.
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2016, 85 (5-8): : 1361 - 1372
  • [8] A BI-OBJECTIVE OPTIMIZATION ALGORITHM FOR AUTOMOBILE MANUFACTURING SCHEDULING
    Alatangaowa, B.
    Batbileg, S.
    Enkhbat, R.
    INTERNATIONAL JOURNAL OF SIMULATION MODELLING, 2020, 19 (01) : 146 - 156
  • [9] Bi-objective optimization of maintenance scheduling for power systems
    B. Hadjaissa
    K. Ameur
    S. M. Ait cheikh
    N. Essounbouli
    The International Journal of Advanced Manufacturing Technology, 2016, 85 : 1361 - 1372
  • [10] Bi-objective optimization of a project selection and adjustment problem under risk controls
    Heidari-Fathian, Hassan
    Davari-Ardakani, Hamed
    JOURNAL OF MODELLING IN MANAGEMENT, 2020, 15 (01) : 89 - 111