COMPARATIVE ANALYSIS WITH THE PERT METHOD: TIMES CERTAIN VS UNCERTAIN

被引:1
|
作者
Yougbare, Wendpanga Jacob [1 ]
Sory, Boureima [1 ]
Zongo, Moumouni [1 ]
机构
[1] Univ Norbert Zongo, UFR ST, L MIA, Dept Math, Koudougou, Burkina Faso
来源
关键词
PERT method; fuzzy set; fuzzy number; uncertain job duration; central scheduling problem;
D O I
10.17654/0974165824008
中图分类号
O1 [数学];
学科分类号
0701 ; 070101 ;
摘要
Purpose. This study consists in providing mathematical tools for monitoring the construction work of a school building in Banfora, Burkina Faso. Methods. PERT/CPM, probabilistic PERT and fuzzy PERT were used to resolve the operational planning issue. Job durations were obtained from optimistic, likely, pessimistic estimates of these durations. Thebeta distribution was considered for the stochastic case and the random job durations were considered independent. For the fuzzy case, the fuzzy job durations were considered non -interactive. Results. With PERT, the results allowed to have the minimum total duration of the project, the critical path, the critical tasks, the total margins and free margins of tasks. With probabilistic PERT, probability calculations allowed for 90%, 95% and 99% confidence intervals and the probability of meeting the minimum total duration of 30.5%. With fuzzy PERT, the calculations allowed to have the fuzzy number corresponding to the minimum total duration. Conclusion. The results obtained show that the three approaches are complementary in a problem of operational planning and monitoring of works such as the case of building construction.
引用
收藏
页码:115 / 134
页数:20
相关论文
共 50 条
  • [1] UNCERTAIN VS A CERTAIN PROSPECT
    EILON, S
    [J]. OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1975, 3 (03): : 354 - 355
  • [2] Achieving A Certain Major Achievement During Uncertain Times
    Sarkar, Indra Neil
    [J]. JAMIA OPEN, 2020, 3 (01) : 1 - 1
  • [3] A method for setting buffer times between batches with uncertain processing times
    Kawano, Koji
    Hasebe, Shinji
    [J]. KAGAKU KOGAKU RONBUNSHU, 2007, 33 (04) : 354 - 362
  • [5] Bank credit in uncertain times: Islamic vs. conventional banks
    Bilgin, Mehmet Huseyin
    Danisman, Gamze Ozturk
    Demir, Ender
    Tarazi, Amine
    [J]. FINANCE RESEARCH LETTERS, 2021, 39
  • [6] ESTIMATION OF TASK COMPLETION TIMES WITH THE USE OF THE PERT METHOD ON THE EXAMPLE OF A REAL CONSTRUCTION PROJECT
    Plebankiewicz, E.
    Juszczyk, M.
    Malara, J.
    [J]. ARCHIVES OF CIVIL ENGINEERING, 2015, 61 (03) : 51 - 62
  • [7] Online Comparison System with Certain and Uncertain Criteria Based on Multi-criteria Decision Analysis Method
    Ziemba, Pawel
    Jankowski, Jaroslaw
    Watrobski, Jaroslaw
    [J]. COMPUTATIONAL COLLECTIVE INTELLIGENCE, ICCCI 2017, PT II, 2017, 10449 : 579 - 589
  • [8] Risk analysis of construction duration based on improved probability analysis method in PERT
    Huang JianWen
    Wang XingXia
    Zhou YiHong
    [J]. PROCEEDINGS OF 2008 INTERNATIONAL CONFERENCE ON RISK AND RELIABILITY MANAGEMENT, VOLS I AND II, 2008, : 295 - 299
  • [9] HISTORICISM VS HISTORY - THE COMPARATIVE METHOD
    GRAY, B
    [J]. JOURNAL OF SOCIAL AND BIOLOGICAL STRUCTURES, 1983, 6 (03) : 193 - 206
  • [10] Mechanical thrombectomy vs catheter directed thrombolysis vs anticoagulation alone: A tertiary center PERT Registry Cohort Analysis
    Kattih, Zein
    Meredith, Simon
    Roselli, Victoria
    Dong, Vincent
    Varkey, Ashwin
    Saini, Amandeep
    Thampi, Shankar
    Leung, Tungming
    Kodra, Arber
    Kliger, Chad
    Mina, Bushra
    [J]. THROMBOSIS RESEARCH, 2024, 241