Case Study: Testing the Overall Efficiency of Equipment in the Production Process in TX Plant Simulation Software

被引:9
|
作者
Pekarcikova, Miriam [1 ]
Trebuna, Peter [2 ]
Kliment, Marek [2 ]
Trojan, Jozef [1 ]
Kopec, Jan [1 ]
Dic, Michal [1 ]
Kronova, Jana [1 ]
机构
[1] Tech Univ Kosice, Fac Mech Engn, Dept Ind & Digital Engn, Kosice, Slovakia
[2] Tech Univ Kosice, Dept Ind & Digital Engn, Kosicec, Slovakia
关键词
Process; Simulation; Efficiency; TX Plant Simulation; OEE; Energy consumption; DATA ANALYTICS; LOGISTICS; SYSTEM; TIME;
D O I
10.24425/mper.2023.145364
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The article deals with a widely used method of measuring the overall efficiency of equipment (OEE), which in combination with technologies and software tools is gaining in importance. The overall efficiency of OEE equipment is a key performance metric for machines and equipment to identify hidden capacities and increase production productivity. The intensification of Industry 4.0 in traditional manufacturing companies supports and creates the conditions for their transformation into a smart factory. The integration of intelligent machines and devices with complex human-machine communication network systems requires a new direction in measuring and increasing OEE. Mass customization, resp. personalization of production raises a high need to monitor, improve and further maintain productivity. The aim of the article is to create a simulation model of the production process and test the energy consumption of selected equipment using TX Plant Simulation software with a proposal of measures to increase the OEE of the company.
引用
收藏
页码:34 / 42
页数:9
相关论文
共 50 条
  • [1] Overall equipment efficiency of Flexographic Printing process: A case study
    Zahoor, S.
    Shehzad, A.
    Mufti, N. A.
    Zahoor, Z.
    Saeed, U.
    [J]. 4TH INTERNATIONAL CONFERENCE ON MECHANICAL, MATERIALS AND MANUFACTURING (ICMMM 2017), 2017, 272
  • [2] Improvement in the overall efficiency of mining equipment: a case study
    Fourie, H.
    [J]. JOURNAL OF THE SOUTHERN AFRICAN INSTITUTE OF MINING AND METALLURGY, 2016, 116 (03) : 275 - 281
  • [3] Simulation Study on Steel Plant Capacity and Equipment Efficiency Based on Plant Simulation
    Deng, Shuai
    Xu, Anjun
    Wang, Hongbing
    [J]. STEEL RESEARCH INTERNATIONAL, 2019, 90 (05)
  • [4] Case study: the simulation modeling to improve the efficiency and performance of production process
    Rosova, Andrea
    Behun, Marcel
    Khouri, Samer
    Cehlar, Michal
    Ferencz, Vojtech
    Sofranko, Marian
    [J]. WIRELESS NETWORKS, 2022, 28 (02) : 863 - 872
  • [5] Case study: the simulation modeling to improve the efficiency and performance of production process
    Andrea Rosova
    Marcel Behun
    Samer Khouri
    Michal Cehlar
    Vojtech Ferencz
    Marian Sofranko
    [J]. Wireless Networks, 2022, 28 : 863 - 872
  • [6] ROBOT AND PLANT SIMULATION FOR AUTOMOTIVE PART PRODUCTION PROCESS DESIGN: A CASE STUDY
    Supsomboon, S.
    Varodhomwathana, T.
    [J]. INTERNATIONAL JOURNAL OF SIMULATION MODELLING, 2017, 16 (04) : 617 - 629
  • [7] Overall Equipment Efficiency Improvement through a Lean Approach in SME: A Case Study
    Dahab, Amr
    Younes, Mohammed A.
    Backar, Soheir
    [J]. INTERNATIONAL JOURNAL OF ENGINEERING RESEARCH IN AFRICA, 2023, 65 : 117 - 129
  • [8] Application of Process Metrics for Software Testing: A Case Study
    Fuentes, Brenda Aymerich
    Cersosimo, Michelle
    Jenkins, Marcelo
    [J]. V JORNADAS COSTARRICENSES DE INVESTIGACION EN COMPUTACION E INFORMATICA (JOCICI 2021), 2021,
  • [9] Command and Software Management Simulation for the Spacecraft Equipment Testing
    Nozhenkova, Ludmila
    Isaeva, Olga
    Vogorovskiy, Rodion
    [J]. PROCEEDINGS OF THE 2018 3RD RUSSIAN-PACIFIC CONFERENCE ON COMPUTER TECHNOLOGY AND APPLICATIONS (RPC), 2018,
  • [10] A Case Study on Testing CMM Uncertainty Simulation Software (VCMM)
    Abackerli, Alvaro Jose
    Pereira, Paulo Henrique
    Calonego, Nivaldi, Jr.
    [J]. JOURNAL OF THE BRAZILIAN SOCIETY OF MECHANICAL SCIENCES AND ENGINEERING, 2010, 32 (01) : 8 - 14