Effects of the Excavation of a Hydraulic Tunnel on Groundwater at the Wuyue Pumped Storage Power Station

被引:2
|
作者
Jiang, Tong [1 ]
Pei, Xun [2 ]
Wang, Wenxue [3 ]
Li, Longfei [2 ]
Guo, Shihao [2 ]
机构
[1] North China Univ Water Resources & Elect Power, Henan Joint Int Res Lab Collapse Landslide Debris, Zhengzhou 450046, Peoples R China
[2] North China Univ Water Resources & Elect Power, Coll Geosci & Engn, Zhengzhou 450046, Peoples R China
[3] North China Univ Water Resources & Elect Power, Henan Key Lab Rock & Soil Mech & Struct Engn, Zhengzhou 450046, Peoples R China
来源
APPLIED SCIENCES-BASEL | 2023年 / 13卷 / 08期
基金
中国国家自然科学基金;
关键词
pumped storage; Wuyue Reservoir; transient numerical simulation; parameter inversion; seepage field; PERMEABILITY; DRAINAGE;
D O I
10.3390/app13085196
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
The tailwater tunnel of the Wuyue pumped storage power station is located in bedrock and extends to depths between tens and hundreds of meters. It is impossible to analyze and evaluate the whole engineering area from geological exploration data, and the hydrogeological conditions are complicated. In the early stages of the tailwater tunnel's construction, the drinking water wells in four villages dried up. This paper reports the results from a field investigation, in situ tests, laboratory tests, and numerical simulation carried out to determine how the groundwater was affected when the tunnel was excavated. A hydrogeological model of the region was established from the inverted regional natural flow field parameters. The model was validated, and an analysis of the errors showed that there was an average error of 1.98% between the natural flow field and the hydrogeological survey flow field. The model was then used to simulate the three-dimensional transient seepage fields under normal seepage conditions and limited seepage conditions, as far as was practical. The results showed that, as the excavation of the tailwater tunnel advanced, the water inflow to the tunnel also increased. When the water inflow increased from 1000 to 5000 m(3)/d, the water level at a distance of 100 m from the axis of the tunnel dropped from -0.956 to -1.604 m. We then analyzed how the water level changed as the water inflow varied and proposed a formula for calculating the extent of the influence on the groundwater. We studied how the water level changed at different well points to ascertain how a groundwater well became depleted and determined the factors that influenced seepage in the regional flow field. The water level in different areas of the project area was simulated and analyzed, and the extent of the groundwater area affected by the tunnel construction was clarified. We then studied how the groundwater in different areas of, and distances from, the project area was influenced by normal seepage conditions and limited seepage conditions and proposed a formula for calculating the extent of the influence on groundwater for different water inflows. We constructed a 'smart site' for visualizing data, sharing information, and managing the project. Time-frequency domain analysis was applied to explore the extent of the impacts and range of the vibration effects on residential housing at different distances from the project area caused by the different methods for excavating the tailwater tunnel. The results from this analysis will provide useful insights into how the excavation of this tailwater tunnel will impact the local residents and living areas.
引用
收藏
页数:21
相关论文
共 50 条
  • [1] CONSTRUCTION OF SHIMOGO PUMPED STORAGE HYDROELECTRIC POWER STATION - EXCAVATION OF INCLINED TUNNELS BY TUNNEL BORING MACHINE.
    Nishida, Tsutomu
    Civil engineering in Japan, 1983, 22 : 110 - 126
  • [2] Study on Granite Permeability Zoning Based on Electrical Resistivity: Take Wuyue Pumped Storage Power Station as an Example
    Huang, Zhiquan
    Ran, Tao
    Dong, Jinyu
    Yuan, Guangxiang
    Zhao, Guizhang
    GEOFLUIDS, 2022, 2022
  • [3] Hydraulic design study for intake/outlet of pumped storage power station
    Li, H
    HYDRAULICS OF RIVERS, WATER WORKS AND MACHINERY, VOL 1, THEME D, PROCEEDINGS: 21ST CENTURY: THE NEW ERA FOR HYDRAULIC RESEARCH AND ITS APPLICATIONS, 2001, : 810 - 817
  • [4] The hydraulic design of pump turbine for Xianyou pumped storage power station
    Zheng, J. S.
    Liu, W. C.
    Fu, Z. Y.
    Shi, Q. H.
    26TH IAHR SYMPOSIUM ON HYDRAULIC MACHINERY AND SYSTEMS, PTS 1-7, 2013, 15
  • [5] Analysis of the high pressure tunnel of the Guangzhou pumped storage power station
    Guangdong Provincial Design Institute of Water Conservancy and Electric Power, Guangzhou, China
    不详
    Proc Inst Civ Eng Water Marit Energ, 1 (25-31):
  • [6] Analysis of the high pressure tunnel of the Guangzhou pumped storage power station
    Lu, ZK
    Wrobel, LC
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-WATER MARITIME AND ENERGY, 1997, 124 (01): : 25 - 31
  • [7] Evolution of hydraulic losses in the side inlet and outlet of a pumped storage power Station
    Guo, Miao
    Huang, Zihao
    Song, Ruixiang
    Jiang, Ziyun
    Wang, Wei
    Guo, Chao
    Shuili Xuebao/Journal of Hydraulic Engineering, 2024, 55 (12): : 1461 - 1471
  • [8] Influence of Bifurcation Pipe Position on Hydraulic Turbulence for Pumped Storage Power Station
    Cao, Linning
    Li, Zhaowen
    Li, Yong
    Li, Bing
    3RD INTERNATIONAL CONFERENCE ON AIR POLLUTION AND ENVIRONMENTAL ENGINEERING, 2020, 631
  • [9] Pumped storage technology combined with thermal energy storage – Power station and pressure tunnel concept
    Pumpspeichertechnologie kombiniert mit thermischer Energiespeicherung – Kraftwerks- und Druckstollenkonzept
    1600, Ernst und Sohn (10):
  • [10] Hydraulic-mechanical coupling vibration performance of pumped storage power station with two turbine units sharing one tunnel
    Guo, Wencheng
    Wu, Fulin
    JOURNAL OF ENERGY STORAGE, 2022, 53