Unrelated parallel machine energy-efficient scheduling considering sequence-dependent setup times and time-of-use electricity tariffs

被引:2
|
作者
Sanati, Hemen [1 ]
Moslehi, Ghasem [1 ]
Reisi-Nafchi, Mohammad [1 ]
机构
[1] Isfahan Univ Technol, Dept Ind & Syst Engn, Esfahan 8415683111, Iran
关键词
Energy-efficient scheduling; Mixed-integer linear programming; Fix and relax; Sequence-dependent setup time; Tariffs; HYBRID FLOW-SHOP; ALGORITHM; MODEL; CONSUMPTION; FIX;
D O I
10.1016/j.ejco.2022.100052
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
Given that about half of the produced energy in the world is consumed in industries, there has been an increasing con-cern about optimizing energy consumption in manufacturing sectors. As one of the most effective ways, proper produc-tion scheduling to reduce energy consumption is of crucial importance among researchers and manufacturers. This pa-per addresses an unrelated parallel machine energy-efficient scheduling problem with sequence-dependent setup times by considering different energy consumption tariffs. The setup times are studied in two modes: disjointed from/jointed to processing time. For each one of these problems, two mixed -integer linear programming models have been formulated. The presented models for the problem with setup time disjointed from processing time can solve up to 16 machines and 45 jobs. In contrast, this capability is changed to 20 machines and 40 jobs for processing time jointed to the setup time problem. Furthermore, a fix and relax heuristic algorithm is presented for large-size instances, which can solve instances of up to 20 machines and 100 jobs for each of the two considered prob-lems. (c) 2022 The Author(s). Published by Elsevier Ltd on behalf of Association of European Operational Research Societies (EURO). This is an open access article under the CC BY-NC-ND license