Solving the unrelated parallel batch machine scheduling problem with mixed-integer programming

被引:0
|
作者
Bakir, Merve [1 ]
Sebatli-Saglam, Asli [1 ]
Cavdur, Fatih [1 ]
机构
[1] Bursa Uludag Univ, Milhendisl Fak, Endustri Muhendisligi Bolumu, Bursa, Turkey
来源
关键词
Unrelated parallel batch processing; machine scheduling; total flow time; makespan; total tardiness; mixed-integer programming; ITERATED GREEDY ALGORITHM; NONIDENTICAL JOB SIZES; TOTAL FLOW TIME; PROCESSING MACHINES; MINIMIZING MAKESPAN; WEIGHTED-TARDINESS; RELEASE TIMES; MINIMIZATION; CAPACITIES; EARLINESS;
D O I
10.2339/politeknik.996529
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
In this study, the problem of scheduling jobs with arbitrary sizes and non-zero release times on a set of unrelated parallel batch processing machines with different capacities is discussed. Three mixed-integer programming models with different objective functions are developed to solve the problem. Corresponding models aim at minimizing (i) the total flow time, (ii) the makespan and (iii) the total tardiness, respectively, which are considered to be among the most important objectives in scheduling problems. In order to test the validity and applicability of the proposed solution approach, different datasets are generated using some rules in the literature. The results obtained by solving the mathematical programming models with these data sets are analyzed in terms of some performance parameters.
引用
收藏
页码:653 / 663
页数:13
相关论文
共 50 条
  • [1] Mixed-integer programming for unrelated parallel machines scheduling problem considering electricity cost and makespan penalty cost
    Cheng, Junheng
    Wu, Peng
    Chu, Feng
    PROCEEDINGS OF THE 2019 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM 2019), 2019, : 802 - 806
  • [2] A constraint programming approach for solving unrelated parallel machine scheduling problem
    Gedik, Ridvan
    Kalathia, Darshan
    Egilmez, Gokhan
    Kirac, Emre
    COMPUTERS & INDUSTRIAL ENGINEERING, 2018, 121 : 139 - 149
  • [3] A Mixed-Integer Programming Model for Parallel Machine Scheduling with Controllable Processing Time
    Mardan, Ehsan
    Tavakkoli-Moghaddam, Reza
    Tabrizi, Babak H.
    PROCEEDINGS OF INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM'2011): INNOVATIVE APPROACHES AND TECHNOLOGIES FOR NETWORKED MANUFACTURING ENTERPRISES MANAGEMENT, 2011, : 60 - 65
  • [4] Solving the Traveling Telescope Problem with Mixed-integer Linear Programming
    Handley, Luke B.
    Petigura, Erik A.
    Misic, Velibor V.
    ASTRONOMICAL JOURNAL, 2024, 167 (01):
  • [5] Solving the Unrelated Parallel Machine Scheduling Problem with Additional Resources Using Constraint Programming
    Arbaoui, Taha
    Yalaoui, Farouk
    INTELLIGENT INFORMATION AND DATABASE SYSTEMS, ACIIDS 2018, PT II, 2018, 10752 : 716 - 725
  • [6] An improved mixed-integer programming approach for bi-objective parallel machine scheduling and location
    Wu, Peng
    Wang, Yun
    Cheng, Junheng
    Li, Yantong
    COMPUTERS & INDUSTRIAL ENGINEERING, 2022, 174
  • [7] Application of Mixed-Integer Programming and Dispatching Rules on Parallel Machine Scheduling with Inserted Idle Time
    Tsai, Chi-Yang
    Wang, Yi-Chen
    INDUSTRIAL DESIGN AND MECHANICS POWER II, 2013, 437 : 748 - 751
  • [8] Mixed-integer linear programming and constraint programming formulations for solving distributed flexible job shop scheduling problem
    Meng, Leilei
    Zhang, Chaoyong
    Ren, Yaping
    Zhang, Biao
    Lv, Chang
    COMPUTERS & INDUSTRIAL ENGINEERING, 2020, 142
  • [9] Mixed-integer programming models for simultaneous batching and scheduling in multipurpose batch plants
    Lee, Hojae
    Maravelias, Christos T.
    COMPUTERS & CHEMICAL ENGINEERING, 2017, 106 : 621 - 644
  • [10] Batch versus cyclic scheduling of flexible flow shops by mixed-integer programming
    Sawik, Tadeusz
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2012, 50 (18) : 5017 - 5034