U.S. Steel Fairfield Works upgrades powerhouse to a distributed control system

被引:0
|
作者
Owen, M. Pittman [1 ]
Story, Matt [2 ]
机构
[1] Utilities
[2] Fairfield Works, U.S. Steel Group, USX Corp., Fairfield, AL, United States
来源
AISE Steel Technology | 2000年 / 77卷 / 07期
关键词
Blast furnaces - Boiler control instruments - Distributed parameter control systems - Electric power generation - Integrated control - Natural gas;
D O I
暂无
中图分类号
学科分类号
摘要
In 1996, a distributed control system (DCS) was installed at the Fairfield Works powerhouse, replacing a host of 1980s vintage analog electronic controls. The new DCS enables much improved control of boilers which produce the cold blast for the No.8 blast furnace as well steam for plantwide use and for turbines used to generate in-plant power. Quantifying return on investment over the three-year operating period through 1999 is difficult because of changes in the costs of purchased power and natural gas. Overall, there has been a substantial reduction in the use of natural gas and a significant drop in the amount of purchased power.
引用
收藏
页码:56 / 59
相关论文
共 50 条
  • [1] Hot dip galvanizing line at U.S. Steel, Fairfield Works
    Anon
    [J]. Iron and Steel Engineer, 1997, 74 (08): : 71 - 73
  • [2] Managing for project excellence - AGC and electrical modernization of U.S. steel Fairfield works' 6-stand cold mill
    Atkinson, J.L.
    Nagy, P.J.
    Donnison, G.T.
    [J]. Iron and Steel Engineer, 1995, 72 (09):
  • [3] Automatic coal bulk density control at U.S. Steel's Clairton Works
    Best, Michael H.
    Rohaus, David M.
    Senchur, Robert L.
    Zowacki, Michael P.
    [J]. AISE Steel Technology, 2000, 77 (01): : 40 - 42
  • [4] North Central U.S.: paper powerhouse
    [J]. Swann, Charles, 2001, PIMA, Mount Prospect, IL, United States (83):
  • [5] U.S. military upgrades with HDPE pipe
    Cooper, Steve
    [J]. Water and Wastes Digest, 2009, 49 (07): : 32 - 35
  • [6] U.S. bomber plans focus on upgrades
    [J]. Aviation Week and Space Technology (New York), 1999, 150 (10):
  • [7] Flatness control and bending systems improve product quality at U.S. Steel Fairless Works
    Trautwig, Hans-Juergen
    Carnevale, Frank
    Hannan, Paul
    [J]. Iron and Steel Engineer, 1999, 76 (08): : 21 - 26
  • [8] Upgrade of U.S. steel's gary works slab handling facilities
    Luther, R.D.
    Kellen, D.L.
    [J]. Iron and Steel Engineer, 1993, 70 (09):
  • [9] U.S. upgrades Lajes field as key staging area
    [J]. Aviation Week and Space Technology (New York), 1994, 141 (22):
  • [10] NSTX-U Control System Upgrades
    Erickson, K. G.
    Gates, D. A.
    Gerhardt, S. P.
    Lawson, J. E.
    Mozulay, R.
    Sichta, P.
    Tchilinguirian, G. J.
    [J]. FUSION ENGINEERING AND DESIGN, 2014, 89 (06) : 853 - 858