Study on Construction Monitoring of Curved Prestressed Concrete Roof Box Girder

被引:0
|
作者
Bu L. [1 ]
Zheng M. [1 ]
机构
[1] College of Civil Engineering, Hunan University, Changsha
关键词
Box girder; Construction monitoring; Construction simulation; Prestressed concrete;
D O I
10.16339/j.cnki.hdxbzkb.2017.07.010
中图分类号
学科分类号
摘要
Construction monitoring is related to the safety of engineering structure. However, the research of construction monitoring is limited in building engineering involved with curved prestressed concrete box girder. Combined with engineering practice of a student activity center venue, the monitoring scheme was made and conducted to ensure the safety in erection process for the curved box girder subjected to large force at the same time, and to keep tracking the whole process of construction. Construction simulation for a butterfly-shaped roof structure of the venue was conducted based on Midas Gen finite element software. According to the actual construction process and the element birth and death technology, the stress and displacement changing tendency of the roof box girder were analyzed in detail. The results derived by the monitoring and simulation were compared. The results show that the simulation method was validated by the good agreement between the results obtained from monitoring and simulation. The stress and displacement of the box girder are in control, and the construction scheme can satisfy the need of construction. The research results provide important reference for the design and construction of the similar large profiled component in building engineering. © 2017, Editorial Department of Journal of Hunan University. All right reserved.
引用
收藏
页码:78 / 85
页数:7
相关论文
共 13 条
  • [1] Li B., Large span prestressed concrete continuous beam bridge's construction control, pp. 6-7, (2012)
  • [2] Wang J., Fang Z., Construction control for large-span prestressed concrete continuous girder bridge, Journal of Hunan University: Natural Sciences, 30, 3, pp. 130-133, (2003)
  • [3] Yang M., Chen Z., An analysis of construction stages simulation for self-anchored suspension bridges, Journal of Hunan University: Natural Sciences, 33, 2, pp. 26-30, (2006)
  • [4] Mooney M.A., Tawfik E.F., Chan G.B., Et al., Health monitoring during vibratory plate compaction of soil, Proceedings of the SPIE, Smart Structures and Materials 2002, Smart Systems for Bridges, Structures, and Highways, pp. 112-123, (2002)
  • [5] Iwaki H., Yamakawa H., Shiba K., Et al., Structural health monitoring system using fbg-based sensors for a damage tolerant building, Proceedings of the SPIE, Smart Structures and Materials 2003, Smart Systems and Nondestructive Evaluation for Civil Infrastructures, pp. 392-399, (2003)
  • [6] Zhang S., Luo X., Zhang Q., Numerical simulation analysis and model test for the tension process of hyperbolic cable net structures, Journal of Hunan University: Natural Sciences, 36, 1, pp. 8-13, (2009)
  • [7] Liu H., Chen Z., Niu B., Numerical simulation and in-situ monitoring of pre-stressing construction of suspen-dome structures, Journal of Building Structures, 33, 12, pp. 79-84, (2012)
  • [8] Zeng Z., Zhang Y., Stress monitoring of the large-span steel structure of the National Stadium during unloading, China Civil Engineering Journal, 41, 3, pp. 1-6, (2008)
  • [9] Zhao Z., Chen Z., Wang X., Et al., Simulation and monitoring of whole erection process for the Yujiapu Railway Station Building, Journal of Building Structures, 36, 1, pp. 136-142, (2015)
  • [10] Qian J., Zhang W., Zhao Z., Et al., Simulation and monitoring for the construction of the steel roof of the Peking University Gymnasium, China Civil Engineering Journal, 42, 9, pp. 13-20, (2009)