Risk-Informed Analysis of Nuclear Power Plant Emergency Diesel Generator Returning to Factory for Overhaul

被引:0
|
作者
Wang Y. [1 ]
Gu X. [2 ]
Li Y. [2 ]
Ma C. [1 ]
Deng W. [1 ]
机构
[1] China Nuclear Power Engineering Co., Ltd., Beijing
[2] Jiangsu Nuclear Power Co., Ltd., Lianyungang
来源
关键词
Emergency diesel generators; Probabilistic safety analysis (PSA); Risk-informed;
D O I
10.13832/j.jnpe.2021.06.0225
中图分类号
学科分类号
摘要
In order to support an emergency diesel generator of Tianwan Nuclear Power Plant Units 1 and 2 for returning to the factory for overhaul, this paper proposes an optimization plan for the unavailability recovery time of an emergency diesel generator, and adopts a combination of determinism and probability theory. The risk-informed approach analyzes the feasibility of the optimization plan. The analysis results show that the unavailability recovery time optimization of an emergency diesel generator meets the requirements of relevant regulations and guidelines and traditional engineering analysis, and the risk to the power plant is small and acceptable. An emergency diesel generator can be returned to the factory for overhaul. © 2021, Editorial Board of Journal of Nuclear Power Engineering. All right reserved.
引用
收藏
页码:225 / 229
页数:4
相关论文
共 6 条
  • [1] 6
  • [2] Nuclear Regulatory Commission, An approach for using probabilistic risk assessment in risk-informed decisions on plant-specific changes to the Licensing Basis: Regulatory Guide (RG) 1.174, (1998)
  • [3] Nuclear Regulatory Commission, An approach for plant-specific, risk-informed decisionmaking: technical specifications: Regulatory Guide (RG) 1.177, (1998)
  • [4] (2012)
  • [5] (2012)
  • [6] (2018)