AN EMPIRICAL STUDY ON THE PROBLEMS OF RUNNING DESIGN AND BUILD PROJECTS IN CONSTRUCTION

被引:4
|
作者
Lam, Edmond W. M. [1 ]
Chan, Albert P. C. [1 ]
Chan, Daniel W. M. [1 ]
机构
[1] Hong Kong Polytech Univ, Dept Bldg & Real Estate, Kowloon, Hong Kong, Peoples R China
关键词
Procurement; design-build; problems; cross-comparison; construction; Hong Kong;
D O I
10.1080/15623599.2007.10773091
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
The drawbacks of the traditional design-bid-build procurement system (design then build) have led project participants in the construction industry to opt for alternative procurement systems, like designbuild (D&B) (design and build) to deliver their projects. Previous research reported the better time performance of the D&B method and the benefits of the single-point contact from the contractor. While D&B has been popularly used in some western countries, the identification of problems in running D&B projects can arouse the concern of project stakeholders, namely, clients, contractors and consultants, especially in countries where D&B is at a germinating stage. This paper presents the empirical findings on the problems of running D&B projects from the perspectives of clients, contractors and consultants. Inter-group comparisons reveal that there is generous consensus in problem ranking in the client-consultant and contractor-consultant groups, while significant differences exist between the clients and the contractors on the ranking exercise. Based on a better understanding of the problems faced by the major participants in running D&B projects, the authors suggest further research on identifying the critical success factors for D&B projects in order to enhance the well being of the construction industry at large.
引用
下载
收藏
页码:1 / 15
页数:15
相关论文
共 50 条
  • [1] Potential problems of running design-build projects in construction
    Lam, Edmond W.M.
    Chan, Daniel W.M.
    Chan, Albert P.C.
    HKIE Transactions Hong Kong Institution of Engineers, 2003, 10 (03): : 8 - 14
  • [2] Study on implementing derivative problems of design-build construction projects in Taiwan
    Wang, Dan-Chi
    Wang, Lung-Chang
    Shanghai Jiaotong Daxue Xuebao/Journal of Shanghai Jiaotong University, 2011, 45 (04): : 539 - 546
  • [3] Root Causes of Design-Construction Interface Problems in Iranian Design-Build Projects
    Yeganeh, Azadeh A.
    Azizi, Mojtaba
    Falsafi, Reza
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2019, 145 (12)
  • [4] DESIGN AND BUILD ELECTRICAL SAFETY INTO CONSTRUCTION PROJECTS
    Crow, Daryld Ray
    Liggett, Danny P.
    Mitchem, James E.
    Work, Frank
    2015 IEEE PETROLEUM AND CHEMICAL INDUSTRY COMMITTEE CONFERENCE (PCIC), 2015,
  • [5] Design and build procurement of construction projects: Hybrids in Singapore
    Foo, J
    Low, C
    Goh, BH
    Ofori, G
    PROFITABLE PARTNERING IN CONSTRUCTION PROCUREMENT, 1999, : 383 - 392
  • [6] Risk Management in Engineering and Construction A Case Study in Design-Build Projects in Vietnam
    Phong Thanh Nguyen
    Phu-Cuong Nguyen
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2020, 10 (01) : 5237 - 5241
  • [7] Best-Value Procurement in Design-Bid-Build Construction Projects: Empirical Analysis of Selection Outcomes
    Nguyen, Phuong H. D.
    Lines, Brian C.
    Tran, Dai Q.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (10)
  • [8] Best-Value Procurement in Design-Bid -Build Construction Projects: Empirical Analysis of Selection Outcomes
    Nguyen, Phuong
    Lines, Brian
    Trani, Dan
    CONSTRUCTION RESEARCH CONGRESS 2018: CONSTRUCTION PROJECT MANAGEMENT, 2018, : 126 - 136
  • [9] Problems and Challenges in the Interactions of Design Teams of Construction Projects: A Bibliometric Study
    Galaz-Delgado, Eduardo, I
    Herrera, Rodrigo F.
    Atencio, Edison
    Munoz-La Rivera, Felipe
    Biotto, Clarissa N.
    BUILDINGS, 2021, 11 (10)
  • [10] Impact of Risk on Design-Build Selection for Highway Design and Construction Projects
    Tran, Dai Q.
    Molenaar, Keith R.
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2014, 30 (02) : 153 - 162