SCHEDULING A FLEXIBLE MACHINING CENTER

被引:16
|
作者
ZIJM, WHM
NELISSEN, EHLB
机构
[1] Nederlandse Philips Bedrijven B. V., Centre for Quantitative Methods, Eindhoven
[2] Eindhoven University of Technology, Department of Mathematics and Computer Science, Eindhoven
来源
关键词
D O I
10.1016/0167-188X(90)90049-N
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This paper describes shopfloor scheduling techniques for a highly automated metal cutting machining centre. The machining centre is modelled as a generalized flowshop, i.e. a set of work stations where each work station may contain several parallel machines. Parts visit all work stations in the same order and are processed by at most one machine in each work station (a part may skip a workstation). Constraints on the scheduling problem are imposed by release and due dates for each job. The objective is to minimize maximal lateness. The approach presented in this paper, is based on a decomposition of the generalized flowshop and uses a parallel machine scheduling algorithm as its key building block. The main contribution of this paper is on the latter subject: the development of schedules with the objective to minimize maximal lateness in a parallel machine system with release and due dates. © 1990.
引用
收藏
页码:249 / 258
页数:10
相关论文
共 50 条
  • [1] Flexible scheduling in a machining center through genetic algorithms
    Sakawa, M
    Kato, K
    Mori, T
    COMPUTERS & INDUSTRIAL ENGINEERING, 1996, 30 (04) : 931 - 940
  • [2] Scheduling of a machining center
    Wang, J
    Luh, PB
    MATHEMATICAL AND COMPUTER MODELLING, 1996, 23 (11-12) : 203 - 214
  • [3] With 'simultaneous engineering' to a flexible machining center
    Bergmann, Klaus
    Lehmann, Hansruedi
    Hulst, Justin
    Zeitschrift fuer Wirtschaftlichen Fabrikbetrieb, 1995, 90 (05):
  • [4] AGGREGATE SCHEDULING OF A FLEXIBLE MACHINING AND ASSEMBLY SYSTEM
    KUSIAK, A
    IEEE TRANSACTIONS ON ROBOTICS AND AUTOMATION, 1989, 5 (04): : 451 - 459
  • [5] Study on tool scheduling for machining center in CIMS
    Feng, Xuelian
    Zhou, Wenya
    Chen, Jigang
    Zou, Quanjiang
    Zhang, Xiangyang
    Yang, Xuchang
    Hangkong Gongyi Jishu/Aeronautical Manufacturing Technology, (02): : 14 - 16
  • [6] Research on the Flexible Product Platform Technology of Machining Center
    Zhao, Yanling
    Ma, Suchang
    MATERIALS, MECHANICAL AND MANUFACTURING ENGINEERING, 2014, 842 : 596 - 601
  • [7] Dual-resource Constrained Flexible Machining Workshop Inverse Scheduling Problem
    Wei S.
    Tang H.
    Li X.
    Yang G.
    Zhang J.
    Zhongguo Jixie Gongcheng/China Mechanical Engineering, 2024, 35 (03): : 457 - 471
  • [8] Simultaneous scheduling of workpieces, fixtures and cutting tools within flexible machining cells
    Rahimifard, S
    Newman, ST
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1997, 35 (09) : 2379 - 2396
  • [9] Dynamic Mixed Model Lotsizing and Scheduling for Flexible Machining Lines Using a Constructive Heuristic
    Yue, Lei
    Chen, Yarong
    Mumtaz, Jabir
    Ullah, Saif
    PROCESSES, 2021, 9 (07)
  • [10] AGGREGATE CAPACITATED LOT-SIZE SCHEDULING FOR A CLASS OF FLEXIBLE MACHINING AND ASSEMBLY SYSTEMS
    TOCZYLOWSKI, E
    HINDI, KS
    IIE TRANSACTIONS, 1991, 23 (03) : 259 - 266