138-KV SHUNT CAPACITOR RESEARCH BANK - DESIGN AND EXPERIENCE

被引:1
|
作者
HARDER, JE
HUTCHINSON, DE
RUST, WB
机构
[1] AMER ELECT POWER SERV CORP,COLUMBUS,OH
[2] COLUMBUS SO POWER CO,COLUMBUS,OH
关键词
Capacitor; Fusing; High Voltage; Insulation; Shunt Capacitor; Substation; Surge Arrester;
D O I
10.1109/61.107294
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
A substation capacitor bank incorporating a number of innovations was installed at the Poston Station (Columbus Southern Power Company) and commissioned July 1988. This paper describes the installation including some discussion of the various innovations; comments on the operating experience through mid-January 1989; and reports observations from a staged fault test on November 10, 1988. © 1989 IEEE
引用
收藏
页码:337 / 342
页数:6
相关论文
共 50 条
  • [1] 138-KV 6-PHASE UPRATING OF A 138-KV DOUBLE-CIRCUIT LINE
    GUYKER, WC
    SHANKLE, DF
    [J]. IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1985, 104 (09): : 2547 - 2554
  • [2] DEVELOPMENT OF A 138-KV SUPERCONDUCTING CABLE TERMINATION
    MAUSER, SF
    BURGHARDT, RR
    FENGER, ML
    DAKIN, TW
    MEYERHOFF, RW
    [J]. IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1976, 95 (03): : 909 - 914
  • [3] Modifying existing 138-kV transmission towers to 230-kV capacity
    Wood, Brian C.
    Moore, Timothy L.
    [J]. 2005/2006 IEEE/PES TRANSMISSION & DISTRIBUTION CONFERENCE & EXPOSITION, VOLS 1-3, 2006, : 1139 - +
  • [4] Problems on settings of shunt capacitor bank protection in 500 kV substation
    Wang, Yonghong
    Meng, Rong
    Wang, Yue
    Lin, Rong
    Liu, Teng
    [J]. Dianli Zidonghua Shebei/Electric Power Automation Equipment, 2010, 30 (08): : 144 - 147
  • [5] SHIELD-INTERRUPT OVERVOLTAGES ON 138-KV EXTRUDED DIELECTRIC CABLES
    HASSLER, SP
    POTTER, ME
    REID, WE
    SECREST, SR
    [J]. IEEE TRANSACTIONS ON POWER APPARATUS AND SYSTEMS, 1984, 103 (11): : 3327 - 3333
  • [6] Lightning Performance of 138-kV Transmission Lines: The Relevance of Subsequent Strokes
    Silveira, Fernando H.
    Visacro, Silverio
    De Conti, Alberto
    [J]. IEEE TRANSACTIONS ON ELECTROMAGNETIC COMPATIBILITY, 2013, 55 (06) : 1195 - 1200
  • [7] EFFECTS OF AGING ON PREMOLDED ELASTOMERIC SPLICES FOR 138-KV XLPE CABLE
    STEPNIAK, FM
    BURGHARDT, RR
    BOLIVER, VJ
    SHIMSHOCK, JF
    [J]. IEEE TRANSACTIONS ON POWER DELIVERY, 1987, 2 (03) : 632 - 637
  • [8] Simulation Analysis of Switching of Shunt Capacitor Bank in 220/22 kV Substation
    Jambukar, Amar Arun
    Satarkar, M. F. A. R.
    [J]. PROCEEDINGS OF THE 2018 SECOND INTERNATIONAL CONFERENCE ON INTELLIGENT COMPUTING AND CONTROL SYSTEMS (ICICCS), 2018, : 1554 - 1559
  • [9] Two-Stage, 161-kV, Fuseless Shunt Capacitor Bank
    Nelson, Jeffrey H.
    Rostron, Joseph R.
    Luke, Daniel J.
    [J]. 2014 IEEE PES T&D CONFERENCE AND EXPOSITION, 2014,
  • [10] Power Quality Problems Caused by Termites on 138-kV Underground Cables
    Fuscaldi, Romeu
    Silveira, Fernando H.
    De Conti, Alberto
    Visacro, Silverio
    [J]. INGENIERIA E INVESTIGACION, 2011, 31 : 148 - 152